The invention discloses a fault
fracture zone tunnel-section treatment structure in a TBM construction tunnel and a treatment method in the technical field of treatment of TBM construction tunnel unfavorable geological conditions. The fault
fracture zone tunnel-section treatment structure comprises a tunnel and a fault
fracture zone located in front of a tunnel face. A
pilot tunnel is formed in the center of the tunnel face, the extending direction of the
pilot tunnel is consistent with the extending direction of the tunnel, and the
pilot tunnel penetrates through the whole fault fracture zone; and a pilot tunnel surrounding rock is retained and protected by sprayed concrete, a plurality of grouting
drill holes are formed in the surrounding rock, one ends, away from the center of the tunnel, of the grouting
drill holes exceed the periphery of the tunnel, and grouting materials are arranged in the grouting
drill holes. According to the fault fracture zone tunnel-section treatment structure in the TBM construction tunnel and the treatment method, the mode that the fault fracture zone is firstly reinforced and then tunneled is adopted, the fault fracture zone is changed to be a relatively stable area and then subjected to TBM tunneling, and the characteristics of TBM rapid tunneling and retaining and protecting are
fully developed; and compared with an
existing treatment structure or method, the fault fracture zone tunnel-section treatment structure and the treatment method are higher in efficiency,
safer in operation and lower in cost, and have good social and
economic benefits.