The invention relates to the technical field of piling construction, and mainly relates to a double-tube-sinking and inner-tube-drawing bored cast-in-place
pile construction method and application. The construction method adopts an eccentric moment-adjustable vibrating hammer, a
pile gripper, inner tubes, outer tubes and a piling rack or a hoisting crane. The construction method includes steps that the inner tubes and the outer tubes are clamped by the
pile gripper at first, the vibrating hammer vibrates and stops vibrating after sinking to the required depth, a pile clamping method is changed so that the pile gripper only clamps the inner tubes, a
winch is started so that the vibrating hammer draws the inner tubes in a vibration-
free state until the inner tubes are thoroughly drawn out, soil in the inner tubes cannot be poured out when the inner tubes are statically drawn due to effects of
friction force, then the piling rack or the hoisting crane moves so that the inner tubes are separated from openings of the outer tubes, the vibrating hammer is started to vibrate, the soil in the inner tubes is continuously poured out in a vibration state until the total soil is poured out, reinforcement cages are placed in the outer tubes sunken into the soil, concrete is fully filled in the reinforcement cages, finally, the outer tubes are clamped by a fixture, the vibrating hammer is started, the outer tubes are drawn out by the aid of the vibration effect of the vibrating hammer, and simultaneously, a pile is formed. The double-tube-sinking and inner-tube-drawing bored cast-in-place pile construction method and the application have the advantages that the structure is novel, and construction efficiency is high.