The invention provides an extra-
high voltage alternating current drop point output project optimal
selection method, and includes the steps of: preliminarily determining an extra-
high voltage alternating current drop point 500kV
transformer station range through balance of
electric power and electric quantity, and preliminarily screening drop point 500kV
transformer stations by evaluating influence on 500kV
bus short-circuit current of a near region after an extra-
high voltage drop point; based on the scale of extra-high
voltage transmitting power, forming an extra-high
voltage alternating current drop point output project scheme set, and further screening output project schemes by evaluating influence of each scheme on 1000 and 500 kV
bus short-circuit current of extra-
high voltage transformer stations; and determining a 500kV output project optimal selection scheme through short-circuit current and safety and stability checks. The extra-high
voltage alternating current drop point output project optimal
selection method provided by the invention can effectively remove unreasonable
drop out output schemes by evaluating interactive influence of an extra-high voltage
power grid and 500kV
power grid short-circuit current of a near region, remarkably reduces unnecessary calculation workloads, the schemes have clear and definite
directivity, and thus a reasonable extra-high voltage alternating current drop point output project scheme can be rapidly determined.