The invention discloses a construction method for converting dangerous rock treatment blasting material into dam filling-level burdening. The construction method comprises the following steps that 1),slope
cutting construction is carried out through a
deep hole bench blasting method, and sloping is carried out on
trailing edge mother rock; 2), blast hole drilling operation is performed by using adrilling
machine, and the blast hole drilling angle is the same as the designed
slope angle; 3), the blast holes are filled with explosives in an interval charging mode, and detonating is carried outby adopting a single-hole single-sound
detonation network; and 4), after layered and sectioned excavation, the blasting
slag materials are transferred through a dump
truck, and the blasting
slag materials are pushed to a material taking platform through a bulldozer. By the adoption of the method, the purpose of changing blasting
gradation is achieved by optimizing blasting parameters, the proportion of large-
diameter stones after blasting is increased, and when the large-
diameter stones are blasted and pushed to the material taking platform, stone sources meeting other construction projects are formed by means of collision of the large-
diameter stones, and the purpose of directly applying the blasting
slag materials to dam construction can be achieved.