The invention discloses a
mass flow
high density structure flow entire-tailing cemented filling technology comprising the following steps: allowing entire-tailing
mortar, a cementing agent and proper amount of concentration adjusted water to enter a feed hopper through each
material supply line, wherein said materials are then conveyed to a stirrer, and all ingredients of the filling material are fully evenly stirred so as to prepare the filling
slurry with proper concentration and excellent fluidity, i.e., the structure flow status can be formed; allowing the filling
slurry to finally enter a filling
slurry discharge hopper, wherein the filling slurry can be conveyed to fill underground stope goaf through filling
drill holes and an underground filling
pipe network through self-flow, thus realizing large structure stope non-interrupted
high density self-flow filling, wherein the sand-
lime ratio can be adjusted according to filling body intensity requirements. The
mass flow
high density structure flow entire-tailing cemented filling technology can satisfy large structure stope, high preparation capability, high preparation precision, and high density structure flow entire-tailing
colloid filling requirements, can reduce filling cost, so the goaf filling
tailings final concentration can be above 70-73%; the filing body intensity structure is reasonable, thus enhancing stope back production safety, and providing large
economic benefits and
social benefits.