The invention discloses a presplitting type wall
cutting and filling
stoping method for a thin ore
vein. The presplitting type wall
cutting and filling
stoping method for the thin ore
vein comprises the steps that a presplitting hole is drilled in the interface of the thin ore
vein and surrounding rock on the hanging side or heading side of the wall to be
cut, presplitting blasting is conducted, the ore vein and the surrounding rock of the
cut wall are blasted at different times, and ore drawing or filling is conducted independently; and all the steps are circulated till a whole ore block is extracted. Simultaneous
millisecond blasting is conducted on the presplitting hole and an ore body blasted in the early stage or the surrounding rock of the
cut wall, namely the presplitting hole is blasted firstly and then the ore body or the surrounding rock of the cut wall is blasted. After ore drawing (under the condition that mining is conducted firstly) or filling (under the condition that wall
cutting is conducted firstly), secondary blasting of the surrounding rock is conducted for on-site filling or the ore body is blasted for ore drawing. All the steps are circulated till the whole ore block is extracted. According to the presplitting type wall cutting and filling
stoping method for the thin ore vein, by introducing the presplitting blasting technique into the wall cutting and filling method, separate stoping of ore and
wall rock of the thin ore vein is achieved in the true sense, the
dilution rate of extraction of the thin ore vein is greatly decreased, and the probability of breakage and cost increase which are caused by excessive
dilution of ore is lowered; in addition, the mineral separation technological index can be improved easily, the tailing stacking pressure is relieved, and high
economic benefits and
social benefits are achieved.