The invention discloses a construction method of a continuous composite
beam bridge and the continuous composite
beam bridge. The construction method of the continuous composite
beam bridge includes the following steps that S1, pre-tensioned
prestressed concrete or ultra-high-performance concrete containing coarse aggregate is selected, and a concrete
bridge deck slab in a
hogging moment zone is prefabricated in a factory; S2, a steel beam and a concrete
bridge deck slab in a sagging moment zone are prefabricated in the factory and connected to form a composite beam component; S3, the composite beam component is hoisted and erected on a bridge
pier at the site of the bridge location; S4, the concrete
bridge deck slab in the
hogging moment zone is placed on the composite beam component to be connected with the concrete bridge
deck slab in the sagging moment zone, maintenance is conducted, and then the construction surface on the bridge
deck slab is paved to complete the construction ofthe continuous composite beam bridge. According to the construction method of the continuous composite beam bridge and the continuous composite beam bridge, the technical problems of an existing continuous composite beam bridge that prestressing of the concrete in the
hogging moment zone is poor,
cracking is easy, the compression resistance capacity is weak, consequently, the
bearing capacity of the bridge is affected, and durability is poor can be solved, and the technical problem that the bridge
deck slabs are not combined and thus the field wet construction amount is increased is further solved.