The invention belongs to the technical field of foundation treatment construction, and relates to a collapsible foundation
immersed tube pile forming treatment method. When a collapsible
loess foundation is treated through
immersed tube compaction piles, when shrinkage cavities occur after immersed tubes are pulled out, a long spiral drilling
machine is adopted for conducting rotary excavating on retracted soil in holes for secondary soil discharging, and the beneficial effects of being good in hole forming effect and high in construction work efficiency are achieved. Meanwhile, due to secondary soil discharging after shrinkage cavity treatment, the compaction degree of soil between the piles is reduced, foundation soil is wet and soft and large in
water content, and in order to make up for the compaction effect of the soil between the piles and improve the
water content of the foundation soil, a filler ramming scheme of the next procedure is adjusted into a
pile forming construction method including
lime soil backfilling, heavy hammer ramming, layered filler filling and layered ramming. Due to the fact that
lime is used for filler adding, the cost of the
pile forming method is properly increased compared with a plain soil backfilling ramming pile forming scheme, the construction efficiency of the pile forming method is the same as that of the plain soil backfilling ramming pile forming scheme, and meanwhile the beneficial effects of being good in pile forming effect and effectively improving the foundation soil property are achieved. Compared with the scheme I, the scheme II and the scheme III in the prior art in the third part of the invention, the secondary hole forming and pile forming scheme has the beneficial effects of being economical, efficient, safe, environment-friendly and applicable.