The invention relates to a boring method of geology whose upper portion is a
silt layer and lower portion is a moderately weathered and a slightly weathered
silt strata, which relates to a construction method of
pile foundation boring. The invention aims to solve the problems that prior geology whose upper portion is a
silt layer and lower portion is a moderately weathered silt strata or a slightly weathered silt strata uses an electric
impact drill to
impact to form holes, the boring speed is slow, the efficiency is low, the construction is not done using an
auger drill, mud which is used when
auger construction is prepared by
bentonite or clay, the manhole mud concentration is 1.15-1.25, the manhole mud
viscosity is 18-24S, and the moderately weathered and the slightly weathered silt strata which are arranged on the lower portion of the
pile foundation is punched by the electric
impact drill. Compared with the electric impact drill is solely used to punch, the boring method has faster speed, the upper portion 40mm geology of a
pile hole whose length is 50mm and
diameter is 1.25m is a silt layer, the lower portion is the moderately weathered and the slightly weathered silt strata, and the boring time is only 4-5 days. Compared with the prior art, the cost of the pile hole is capable of being reduced by 50 percent.