The invention discloses a roadbed
karst collapse comprehensive renovation method which comprises the following steps: 1, geology in a line range is explored, and
karst development conditions are determined in combination with drilling
coring and a pressurized-water test; 2, inclined holes and straight holes are drilled in the
karst section, the inclined holes are formed in one row on each side ofthe line and obliquely drilled towards the center of the line, and the straight holes are formed in two rows on each side of the line and located in the outer sides of the inclined holes; 3, after drilling is completed, grouting pipes and
grout return pipes are arranged for the inclined holes and the straight holes, and hole sealing is conducted; and 4, conducting
pressure grouting on the inclinedholes and the straight holes. According to the method, soil cracks and karst caves under the roadbed surface are filled through inclined hole grouting, and roadbed surface collapse under the action of
train loads is prevented; the problem of
subgrade surface collapse caused by soil body fine material loss due to dynamic water change is solved through straight hole waterproof curtain grouting, thesubgrade karst
treatment effect is remarkable, the construction cost is low, the period is short, and the influence on existing railway operation is small.