The invention discloses a fast construction method of a
headframe lifting
system, which belongs to the technology of construction of mines. When a
headframe foundation and a
headframe main body are constructed to about 23 meters, shaft equipment components are processed, large temporary facilities of shaft equipment are arranged, during construction of the headframe main body above about 23 meters, the shaft equipment is mounted, a crane above a hall of an
elevator is hoisted before the headframe main body is finished and the top of the headframe main body is sealed, the crane is installed, and the
elevator is hoisted and mounted after the top of a headframe is sealed. After the top of the headframe is sealed, the constructed headframe is decorated, simultaneously, the
elevator and a sleeve frame in the headframe are mounted, after the headframe equipment is mounted, equipment of upper and lower openings is mounted, ropes are wound and a lifting container is hung after the elevator is mounted, finally, debugging running is carried, and then construction and installation operations of the headframe lifting frame are totally finished. The fast construction method of the headframe lifting
system has the advantages that work hour
utilization rate is high, construction speed is fast, and
engineering quality is improved advantageously. Constructors, equipment and materials are reasonably allocated via parallel cross operation, and
engineering manufacturing cost is lowered.