The invention discloses an excavation and mucking construction process for a tilting type superlarge-section single-
pile foundation. The process comprises the steps of firstly, advanced
pipe shed support construction; secondly, hole mouth protection, i.e., a hole mouth support structure is constructed at a hole mouth of a
pile hole; thirdly, installation of a mucking device at the hole mouth, i.e., the mucking device is installed outside the hole mouth of the
pile hole and comprises a left longitudinal travelling frame, a right longitudinal travelling frame, a transverse travelling frame capable of horizontally moving on the two longitudinal travelling frames front and back, a hoisting device capable of horizontally moving on the transverse travelling frame left and right, and a mucking hopper hoisted below the hoisting device through a
rope; and fourthly, pile hole excavation and mucking construction, i.e., a full section excavation method is adopted for the pile hole excavation with a plurality of construction segments arranged from top to bottom, and the mucking device is used for mucking synchronously in the excavation process of each construction segment. The excavation and mucking construction process for the tilting type superlarge-section single-pile foundation is easy in step, reasonable in design, low in
investment cost, simple and easy to construct, good in use effect and capable of easily and fast completing the excavation and mucking construction process of the tilting type superlarge-section single-pile foundation, and the construction process is safe and easy to control.