The invention relates to the technical field of fabricated
shear wall, and discloses a construction technology process of a fabricated
shear wall structure. The construction technology process comprises the following steps that (1) a PC component enters the site; and (2) before the prefabricated PC component enters the site, the process inspection and tensile strength inspection certificates of areinforcement connection joint are checked. In the construction technology process of the fabricated
shear wall structure, according to the principle of liquid level
pressure balance, if the liquid level of a
slurry discharge hole in a bending section is only settled slightly, the situation that the
slurry at the grouting sleeve is dense can be determined, if a large
sedimentation occurs, the sealing condition of a grouting layer cavity can be checked immediately, the grouting density is ensured, the situation that grouting is not dense is prevented, a plastering free construction technology is adopted, therefore, the surfaces of prefabricated components are correspondingly constructed in accordance with high-precision and clear light during production, so as to avoid
cracking and fallingoff of the decorative surfaces of an external wall in the later stage, the advantages of the prefabricated building are reflected, the requirements of green construction are met, meanwhile the invasion of an internal wall is avoided, and the quality of the shear wall is ensured.