The invention provides a shield construction
system, which includes a shield receiving shaft and a turn-back
belt conveyor assembly, wherein the shield receiving shaft is arranged on the tunneling
route of the
shield machine, and in the direction of tunneling of the
shield machine, the shield The first tunnel and the second tunnel are respectively formed on both sides of the
machine receiving shaft, and the shield receiving shaft is used to initiate the second
shield machine and receive the first shield
machine; at least a part of the return
belt conveyor assembly is arranged in the second tunnel , to be used to automatically transport the
muck produced by the second shield
machine to the ground when excavating the second tunnel; in the direction of shield machine excavation, the width of the part of the return
belt conveyor assembly located in the shield receiving shaft is the same as The ratio of the width of the shield receiving well is greater than 0 and less than or equal to 30%. The invention solves the unreasonable
layout of the belt conveyor and the receiving shaft of the shield machine in the prior art, which causes the shield machine to be unable to be received normally, slows down the progress of the shield machine construction, prolongs the construction period of the shield machine, and improves the construction efficiency of the shield machine. The cost of shield construction.