The invention discloses a construction method of a high-drop deep-water rock-socketed foundation. When the
water level is lower than a predetermined height, the
river bed is cleared to form a foundation pit operation area; a double-wall steel
cofferdam is assembled, and the bottom of the blade foot of the double-wall steel
cofferdam The bottom tray is set, the inner wall is fixed with the bottom section steel casing and the steel
pipe pile of the drilling platform, and the top is provided with a temporary platform, and the wall warehouse is filled with concrete with blade feet; the double-wall steel
cofferdam is put into the river as a whole by the air bag method, After preliminary positioning, the bottom tray is removed; after precise positioning, the double-walled steel cofferdam is sunk and planted on the
bed; construction of sand bag plugging in the steel casing of the bottom section, bottom sealing concrete construction in the cofferdam, removal of the temporary platform; connection of high steel
pipe piles, Set up a drilling platform, insert a small-
diameter tool steel casing into the steel casing of the bottom section, carry out bored
pile construction during the flood period, pour concrete into the double-wall steel cofferdam wall bin in a timely manner, and carry out bearing work after pumping water in the cofferdam during the
dry season. platform construction. The construction efficiency of the method is high, and the
engineering quantity of the drilling platform is small; the small-
diameter tool steel casing can be used backwards, and the construction cost is low.