Concrete pile and preparation method thereof
A concrete pile and concrete technology, applied in the field of concrete piles, can solve problems such as the shortage of sand resources and industrial waste residue pollution, and achieve significant social benefits, reduce environmental hazards, and reduce costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0019] Embodiment 1: Production of PHC concrete pipe piles, the components of the concrete are cementitious material, sand, industrial waste residue, gravel, naphthalene series high-efficiency water reducing agent and water, wherein the cementitious material is cement; wherein, the bulk density of concrete 2500kg / m 3 , the water-binder ratio is 0.3, and the amount of gelling material is 420kg / m 3 The fineness modulus of sand is 3.0, and the sand rate is 36%; the industrial waste slag is steel slag, and its fineness modulus is 2.0, which replaces 20% natural sand; the particle size of gravel is 5-25mm, and the crushing value is 5%; the dosage of water reducing agent is 0.65% of the total gelling material.
[0020] The specific production process is as follows:
[0021] (1) First put sand, industrial waste residue, and cementitious materials into the concrete mixer to mix until uniform, then add 70-90% of the water in the entire formula, and then stir until uniform, and finall...
Embodiment 2
[0026] Embodiment 2: produce PHC concrete pipe pile, its preparation method is the same as embodiment 1, difference is: the component of described concrete is cementitious material, sand, industrial waste residue, crushed stone, polycarboxylate high-performance water reducer and Water, wherein the cementitious material is a mixture of cement and mineral powder according to 1:0.6; among them, the bulk density of concrete is 2400kg / m 3 , the water-binder ratio is 0.3, and the amount of gelling material is 300kg / m 3 The fineness modulus of sand is 3.2, and the sand ratio is 33%; the industrial waste residue is industrial tailings and mine tailings, and its fineness modulus is 0.7, which replaces 50% of natural sand; the particle size of gravel is 5~ 25mm, the crushing value is 5%; the dosage of water reducing agent is 0.3% of the total cementitious material.
Embodiment 3
[0027] Embodiment 3: Production of PHC concrete pipe piles, its preparation method is the same as in Embodiment 1, the difference is that: the components of the concrete are cementitious material, sand, industrial waste residue, gravel, polycarboxylate high-performance water reducer and water, wherein the cementitious material is a mixture of cement and ground sand according to 1:0.5; wherein, the bulk density of concrete is 2600kg / m 3 , the water-binder ratio is 0.35, and the amount of gelling material is 600kg / m 3 The fineness modulus of sand is 3.5, and the sand ratio is 40%; the industrial waste is sandblasting, and its fineness modulus is 1.0, which replaces 10% of natural sand; the particle size of gravel is 5-25mm, and the crushing value 5%; the dosage of water reducer is 0.2% of the total gelling material.
PUM
Property | Measurement | Unit |
---|---|---|
Particle size | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com