Due to the flatness of the sports field foundation, the plastic surface layer paved on site will have different thicknesses after paving. The uneven thickness of the plastic surface layer will lead to different rebound coefficients in various areas of the plastic surface layer on the sports field. Hard unevenness is very common, affecting
athletes' sports experience and easily causing sprains to
athletes;
Pave or spray a certain area of venues after each batch of material is prepared, and then continue to deploy the next batch of materials to pave or spray the next area of venues. A complete sports field needs to be divided into
multiple days and multiple batches of materials. Moreover, all the ingredients are manually operated, and the mixing of various materials creates a lot of uncertainty. The ratio of ingredients in each can is inconsistent, and human errors are large, so it is impossible to ensure that the ratio of each ingredient is consistent.
In the end, the quality of each area of the entire sports field is uneven, the adhesion is inconsistent, and individual areas are seriously vulnerable
[0007]
Disadvantage 3: Poor
predictability. The plastic surface layer of on-site batching and paving needs to purchase a variety of raw materials from material manufacturers, and many different materials are required from the plastic bottom layer to the surface layer.
Moreover, the
material quality of different material manufacturers is also uneven. The performance of the materials prepared by the same ingredient ratio under the influence of different temperature,
humidity, light and other on-site factors is also different. The construction level of each worker in the same construction team is different. Similarly, the quality of the plastic site after construction is uneven, and the overall quality and effect after paving cannot be expected before the actual operation, and the
predictability is poor.
[0008] Disadvantage 4: It is seriously affected by weather and seasons. The plastic surface layer paved with ingredients on site must be constructed in sunny and warm weather. It cannot be constructed in rainy days or winter.
[0009] Disadvantage 5: Long construction period, long maintenance period, and long
waiting period for putting into use
[0010] Disadvantage 6: It is difficult to maintain in the later stage, and the repaired sports field is easy to
cause injury to
athletes. If the plastic surface layer of the on-site material paving is damaged in some areas later, it is difficult to repair. For example, the damaged
runway area is generally
cut in a
square shape. Then remove the plastic layer in the area, and then re-pave the area. Due to the relatively small area, considering factors such as freight, cost, and repair area limitations, construction equipment such as pavers cannot be used for actual repairs. , so all the on-site repairs are done manually, which creates more uncertain factors in it. First of all, is the ratio of materials consistent with the ratio when the plastic track was newly built? Are the brands and quality of various raw materials the same as those used when the plastic
runway was first built? Secondly, can the compaction and adhesion of the plastic repaired by manual construction be compared with that of the original
machine construction? Again, is the elasticity and surface texture consistent with the original? Finally, there will be obvious repair marks at the junction of the old and new plastics, which can easily cause damage to athletes after repairing (the main reasons are as follows: 1. The
height difference between the old and new runways is inconsistent; 2. The difference in density between the old and new runways leads to inconsistent
impact absorption elasticity; 3. Due to the manual partial spraying of the surface layer, the texture of the old and new runways is inconsistent, that is, the anti-skid value is inconsistent)
All of the above situations will lead to difficulties in the later maintenance of the actually paved plastic surface
[0011] 2. Defects in the plastic surface layer of prefabricated coils
[0013] Disadvantage 1: There are many seams and no pertinence. The plastic surface
layers of all existing brands of prefabricated coils are factory-fixed specifications, and the corresponding prefabricated plastic coils will not be produced separately according to the actual situation of the customer's site, and When encountering different color partitions, only two prefabricated coils of different colors can be used to splice together, resulting in too many seams during actual paving, and the splicing phenomenon is serious. The plastic sports field after paving has too many seams, resulting in a The
failure rate increases in the later period, which greatly reduces the service life of the sports field
[0014] Disadvantage 2: There is no
radian and no corner. The existing prefabricated coiled plastic surface is straight when it leaves the factory. When it is paved in the corner area of the sports field, the straight coiled material is deformed into an arc form by external force. , the deformed coil is unevenly stressed inside and outside the inner and outer rings, and the thickness is different, which is easy to cause damage to the athletes
In particular, the
frost heaving coefficient after the change of cold and heat is inconsistent, which leads to the most prone to cracks and bulges at the corners, which greatly reduces the service life of the sports field
[0015] Disadvantage 3: It is difficult to maintain the corner at the later stage, and the sports field after maintenance is easy to
cause injury to athletes
[0019] Disadvantage 1: It is difficult to remove
snow and ice in winter. The surface of the plastic surface of the sports field is a
rough surface with friction, and the texture of the plastic surface is relatively soft. Cause damage, especially after the
snow has melted into ice, it is almost impossible to remove this
thin layer of ice, causing most of the plastic sports fields in the north to be unusable in winter
[0020] Disadvantage 2: The marking line is inaccurate. The marking process after all the plastic surface paving is done manually requires workers to measure the on-site size and draw the proper functional marking line. The
human error is large, which eventually leads to the actual paving The marking line of a good plastic sports field is not accurate
[0021] Disadvantage 3: The site is dirty, messy, and seriously polluted. The large amount of glue used on site and the spraying and marking of the surface will produce a large amount of liquid droplets, which can easily splash onto the surrounding roads and facilities, causing
pollution