Swivel and closure construction method for large-span continuous beam crossing existing station
An existing station and long-span technology, applied in bridges, bridge materials, bridge construction, etc., can solve the problems of heavy beam weight, tight construction period, and large swivel span
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0107] Such as figure 1 Shown is a long-span continuous beam spanning the existing station swivel and closing construction method, the long-span continuous beam constructed is a reinforced concrete box girder spanning the existing station; the front and rear ends of the long-span continuous beam are respectively supported on On the first pier and the fourth pier and the front and rear ends of the middle span are respectively supported on the second pier 1 and the third pier 2, the first pier, the second pier 1, the third pier 2 and the fourth pier are arranged from front to back along the longitudinal bridge direction of the large-span continuous beam being constructed, and they are all reinforced concrete pier, and the second pier 1 and the third pier 2 are respectively located at the Describe the left and right sides of the existing station; the mid-span of the long-span continuous girder constructed is divided into mid-span front side beam section 3-1, mid-span closing sect...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com