Continuous steel truss bridge side span rapid closure construction system and construction method

A technology for steel truss bridges and side spans, which is applied in the field of rapid closure construction system for side spans of continuous steel truss bridges, and can solve problems such as long construction period, high cost measures, safety risks and potential safety hazards

Pending Publication Date: 2019-11-22
四川路桥华东建设有限责任公司
View PDF0 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The three-span continuous steel truss girder structure is generally divided into lower triangular area, upper triangular area, side span, middle span and closing section, and the construction process sequence is lower triangular area→side span→upper triangular area→middle span→closing section. The conventional process of cross-span steel truss girders is installed with a support system, and the installation sequence of side-span steel truss girders is installed from the side-span direction to the mid-span direction. Segmented pre-deflection is adopted, and then the temporary closing section of the side-span steel truss girder is installed and constructed, and finally the installation position and line shape of the steel truss girder are adjusted in segments. This process has a long construction period and high cost measures, and the steel truss girder is adjusted repeatedly The installation location will bring certain safety risks and potential safety hazards

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Continuous steel truss bridge side span rapid closure construction system and construction method
  • Continuous steel truss bridge side span rapid closure construction system and construction method
  • Continuous steel truss bridge side span rapid closure construction system and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0017] The following will be combined with Figure 1-Figure 9 The present invention is described in detail, and the technical solutions in the embodiments of the present invention are clearly and completely described. Apparently, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0018] The present invention provides a continuous steel truss girder bridge side span fast closing construction system through improvement, which can be implemented in the following manner; System 4; wherein, the temporary support pad 3 is composed of a sand bucket 5, a steel pillow 6 and a PTFE slide plate 7, and the temporary support pad 3 is located on the temporary support 2 as a whole; wherein, a reaction force frame is installed on the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a continuous steel truss bridge side span rapid closure construction system and a construction method. The system is provided with a 600t pier-crossing gantry crane, a temporarysupport, a temporary support pad and a reaction frame traction system, wherein the temporary supporting pad is composed of a sand barrel, a steel sleeper and a tetrafluorohydrazine sliding plate, thetemporary supporting pad is integrally located on the temporary support, and a reaction frame traction system is installed on a lower chord of a corresponding temporary closure point and is composedof a reaction frame, a 200t double-acting jack and a PLC synchronous numerical control hydraulic terminal. The method and the system can effectively solve the problem that a temporary closure sectionneeds a matching and cutting process or needs to repeatedly adjust the installation position and the line type of a steel truss girder, reduce the equipment investment, shorten the construction period, save the measure cost and reduce the construction safety risks.

Description

technical field [0001] The invention relates to the field of fast closing construction of side spans of continuous steel truss girder bridges, in particular to a construction system and method for fast closing side spans of continuous steel truss girder bridges. Background technique [0002] The three-span continuous steel truss girder structure is generally divided into lower triangular area, upper triangular area, side span, middle span and closing section, and the construction process sequence is lower triangular area→side span→upper triangular area→middle span→closing section. The conventional process of cross-span steel truss girders is installed with a support system, and the installation sequence of side-span steel truss girders is installed from the side-span direction to the mid-span direction. Segmented pre-deflection is adopted, and then the temporary closing section of the side-span steel truss girder is installed and constructed, and finally the installation pos...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E01D6/00E01D101/30
CPCE01D6/00E01D21/00E01D2101/30
Inventor 周康福杨益平魏鹏飞卜新夏伟杰闵玉刘杰
Owner 四川路桥华东建设有限责任公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products