A construction method and technology of horizontal passage, applied in the construction of horizontal passage and in the field of horizontal passage, can solve the problems of high roof height, construction difficulty and high risk, so as to prevent roof collapse, prevent instability and collapse, and speed up construction. effect of progress
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] A construction method for a horizontal passage leading from a flat pilot hole to a main hole, please refer to Figure 1 to Figure 6 .
[0051] Such as figure 1 As shown, in the construction method of the horizontal passage from the flat pilot tunnel to the main tunnel provided by the embodiment of the present invention, the section of the normal tunnel 11 is larger than the section of the flat pilot tunnel 12, and the flat pilot tunnel 12 is parallel to the normal tunnel 11, and the normal tunnel 11 is a tunnel for building roads or railways, and the flat pilot tunnel 12 is a tunnel for assisting the construction of the main tunnel 11.
[0052] In this embodiment, the sections where the positive tunnel 11 and the pilot tunnel 12 are located are located in a certain area in southwest my country, and the rock masses in the section where the positive tunnel 11 and the flat pilot tunnel 12 are located are V-level surrounding rocks, the stability of the rock masses is poor,...
Embodiment 2
[0096] A horizontal passage leading from a pilot hole to a main hole, see Figure 5 and Figure 6 .
[0097] The construction method of Embodiment 1 is adopted for the cross channel leading from the flat pilot hole to the main hole in the embodiment of the present invention. The lock opening 135 at the intersection of the transverse channel 13 and the main hole 11 is provided with an initial opening supporting steel frame around the initial opening 131, and the locking opening 135 is provided with a locking opening supporting steel frame. From the top of 131 to the top of the intersection with Zhengdong 11, the slope gradually rises along a 20% slope.
[0098] Further, the cross channel 13 also includes a ceiling 111 that transitions from the top of the lock opening 135 to the top of the main hole 11. The ceiling 111 includes a roof support steel frame, and the roof support steel frame The inclined beam 115 extending from the top of the main hole 11, and the locking support...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com