A shield tunneling construction method for water-rich upper soft and lower hard composite strata
A technology of composite strata and construction methods, applied in earth-moving drilling, mining equipment, tunnels, etc., can solve problems such as large differences in physical property indicators, tool wear, etc., to reduce the risk of water inrush, facilitate cutting, and achieve good material adaptation sexual effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] A shield tunneling construction method for a rich water-soft-lower-hard composite stratum, please refer to figure 1 , figure 2 , including the following steps:
[0036] 1) Geological survey
[0037] Before excavation in the shield section, use ground drilling detection or advance geological detection of the shield tunnel face to detect the upper soft and lower hard composite strata (that is, the shield tunnel face) in the shield tunnel face within the excavation range. The upper part of the face is a soft stratum, and the lower part of the shield tunnel face is an interval section of a hard stratum) to carry out geological survey to obtain the geological survey data of this section;
[0038] 2) Determine the cutting area
[0039] According to the geological survey data obtained in step (1), determine the hard stratum region in the face of the shield tunnel, and use the hard stratum region in the face of the shield tunnel as the cutting area 5;
[0040] 3) Cut the a...
Embodiment 2
[0047] Taking the first-phase civil construction construction of a city public transport supporting project in a certain shield tunnel section as an example, the shield tunneling construction method of the present invention is used in the composite stratum with rich water and soft bottom. Please refer to figure 1 , figure 2 , including the following steps:
[0048] 1) Geological survey
[0049] Before excavation in the shield section, use ground drilling detection or advance geological detection of the shield tunnel face to detect the upper soft and lower hard composite strata (that is, the shield tunnel face) in the shield tunnel face within the excavation range. The upper part of the surface is the soft stratum, and the lower part of the shield tunnel face is the interval part of the hard stratum) to carry out geological survey to obtain the geological survey data of this interval, see Table 1 and Table 1 for details. image 3 , Figure 4 ;
[0050] Table 1 The survey res...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com