Construction method of prefabricated septic tank

A construction method and septic tank technology, applied in chemical instruments and methods, anaerobic digestion treatment, water/sludge/sewage treatment, etc., can solve the problems of long construction period, leakage, etc. Strong leakage and good structural stability

Inactive Publication Date: 2019-12-20
广东建宇建筑科技有限公司
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to provide a construction method for prefabricated septic tanks to solve the problems of long construction period and leakage

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0018] A construction method of a prefabricated septic tank includes the following steps:

[0019] Step 1: Determine the construction location and the location of the inspection well according to the geological conditions and the size of the septic tank, and then determine the construction route and sequence;

[0020] Step 2. Leveling and cleaning the site according to the scope of construction requirements, excavating the foundation trench for septic tank installation, and constructing temporary facilities and construction channels at the same time;

[0021] Step 3: Mix the concrete and water according to the proportion, make the mixture wet after mixing, then level the bottom of the base tank, and then lay a gravel cushion on the bottom, and a concrete layer on the upper surface of the gravel cushion;

[0022] Step 4. Then build a septic tank frame on the surface of the concrete layer. The outer surface of the frame is fixed by a fixing frame. The frame is equipped with internal part...

Embodiment 2

[0028] A construction method of a prefabricated septic tank includes the following steps:

[0029] Step 1: Determine the construction location and the location of the inspection well according to the geological conditions and the size of the septic tank, and then determine the construction route and sequence;

[0030] Step 2. Leveling and cleaning the site according to the scope of construction requirements, excavating the foundation trench for septic tank installation, and constructing temporary facilities and construction channels at the same time;

[0031] Step 3: Mix the concrete and water according to the proportion, make the mixture wet after mixing, then level the bottom of the base tank, and then lay a gravel cushion on the bottom, and a concrete layer on the upper surface of the gravel cushion;

[0032] Step 4. Then build a septic tank frame on the surface of the concrete layer. The outer surface of the frame is fixed by a fixing frame. The frame is equipped with internal part...

Embodiment 3

[0038] A construction method of a prefabricated septic tank includes the following steps:

[0039] Step 1: Determine the construction location and the location of the inspection well according to the geological conditions and the size of the septic tank, and then determine the construction route and sequence;

[0040] Step 2. Leveling and cleaning the site according to the scope of construction requirements, excavating the foundation trench for septic tank installation, and constructing temporary facilities and construction channels at the same time;

[0041] Step 3: Mix the concrete and water according to the proportion, make the mixture wet after mixing, then level the bottom of the base tank, and then lay a gravel cushion on the bottom, and a concrete layer on the upper surface of the gravel cushion;

[0042] Step 4. Then build a septic tank frame on the surface of the concrete layer. The outer surface of the frame is fixed by a fixing frame. The frame is equipped with internal part...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a prefabricated septic tank. The construction method of the prefabricated septic tank comprises the following steps: determining a construction position and the position of an inspection well; carrying out field leveling cleaning, and excavating a foundation ditch for mounting a septic tank; mixing concrete with water in proportion, and then enabling the mixture to be in a wet state, leveling the bottom of the foundation ditch, laying a broken stone hardcore on the bottom, and laying a concrete layer on the upper surface of the broken stone hardcore; then building a frame of the septic tank on the surface of the concrete layer, and meanwhile prefabricating a cover plate; pouring prepared concrete into an inner partition plate of the frame, standing for 8-14 hours, and then sequentially disassembling a fixing rack, the frame and the inner partition plate; mounting a connecting pipeline according to a construction drawing, and covering theseptic tank with the cover plate after a water closing test is qualified; and carrying out sealing, earthwork backfilling and tamping, and finally checking. The construction method of the prefabricated septic tank is good in structural stability, high in seepage resistance, small in engineering quantity, short in period and convenient to construct, and mounting can be implemented along with excavation.

Description

Technical field [0001] The invention belongs to the technical field of building construction, and specifically relates to a construction method of a prefabricated septic tank. Background technique [0002] Septic tank is a kind of equipment for processing and distinguishing and filtering sediment. The principle is that the solidified substance decomposes at the bottom of the pool, and the upper layer of hydrated objects enters the pipeline and flows away, preventing the pipeline from being blocked and giving the solidified substance (feces and other garbage) sufficient time to hydrolyze. Septic tank refers to a small processing structure that separates and settles domestic sewage and anaerobic digestion of sludge. Most of the existing septic tank construction methods have long periods and often leaks. Therefore, a new type of prefabricated septic tank construction method is needed to solve the above problems and meet people's needs. Summary of the invention [0003] The purpose ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): C02F3/28C02F11/04
CPCC02F3/2866C02F11/04
Inventor 黄国响陈从瑶黄绍有潘祥军宋震峰
Owner 广东建宇建筑科技有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products