Novel connecting structure for subway tunnel and extended station and construction method of novel connecting structure
A technology for connecting structures and tunnels, applied in infrastructure engineering, tunnels, underwater structures, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] like figure 1 and 2 As shown, the present invention is a novel connecting structure between a subway tunnel and an extended station, comprising a tunnel gallery piece 1, a rail base 1-1, a load-bearing column 2, a prefabricated first bottom plate 3 on the bottom surface, a prefabricated second bottom plate 4 on the bottom surface, and a prefabricated bottom surface The third bottom plate 5, concrete leveling layer 6, waterproof material layer 7, prefabricated second bottom plate 8 on the top surface, prefabricated third bottom plate 9 on the top surface, prefabricated first bottom plate 10 and post-casting belt 11 on the top surface, special shield tunnel tube Corridor 1 is composed of 6 prefabricated standard segments a-f, and the connection sequence is clockwise from a to f, among which the standard segments a and b that are dismantled later form the opening of the platform.
Embodiment 2
[0030] like image 3 and 5As shown, the connection between the special segment and the transfer station structure is divided into a top connection block and a bottom connection block. It consists of cast belt 11, the bottom prefabricated first base plate 3 is arranged on one side of the load-bearing column 2, the bottom prefabricated second base plate 4 and the bottom surface prefabricated third base plate 5 are arranged on the other side of the load-bearing column 2, the bottom prefabricated second floor is divided into The horizontal part 4-1, the vertical part 4-2 and the bending support part 4-3, the vertical part 4-2 and the prefabricated third base plate 5 on the bottom surface correspond to the connection gap to form a groove 4-4, and the post-casting tape is used later 11 connections.
Embodiment 3
[0032] like Figure 4 and 6 As shown, the top connecting block connection is composed of the top prefabricated first bottom plate 10, the top prefabricated second bottom plate 8, the top prefabricated third bottom plate 9 and the post-casting belt 11, and the top prefabricated first bottom plate 10 is arranged on the load-bearing column 2, the top prefabricated second bottom plate 8 and the top prefabricated third bottom plate 9 are arranged on the other side of the load-bearing column 2, and the top prefabricated second floor is divided into a horizontal part 8-1 and a vertical part 8-2 And the bending support part 8-3, the vertical part 8-2 and the prefabricated third bottom plate 9 on the top surface correspond to the connection gap to form a groove 4-4, and then use the post-casting tape 11 to grout the connection, and add a case in the grout Water-expandable waterproof glue, concrete troweling layer 6 is set at the bottom of the tunnel pipe gallery, and the height is equ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com