A construction method for reverse installation of a hanging steel structure

A construction method and technology for steel structures, applied in building construction, building material processing, construction, etc., can solve the problems of difficulty in lifting steel trusses, difficult to control the lateral stability of arc main trusses, and large spans, etc. Effective set-up and dismantling, achieving the effect of graded crossing operations, reducing the need for working faces

Active Publication Date: 2019-06-14
CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the development of the national economy and the diversification of architectural design, more and more space special-shaped steel truss structures are used in various large-scale stadium buildings. Developed from the ground to be installed on the roof of the concrete building, cross-construction with other professions, the space available for hoisting is very small, and the conventional hoisting process cannot solve such problems
[0003] At present, during the construction of steel truss structure buildings, it is difficult to lift the steel truss from bottom to top. Under the condition of narrow space, it cannot be hoisted directly on the reinforced concrete structure floor, and the arc-shaped main truss is laterally stable during the hoisting process. It is not easy to control; high-altitude assembly and welding operations and three-dimensional crossing operations are large, requiring a large number of mechanical shifts and supporting tire frames, which are high in cost and low in efficiency; when the segmented truss is lifted and installed, the lateral stability of the arc-shaped main truss is difficult to control ; The problem of easy deformation and instability during the hoisting of multi-level steel trusses

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method for reverse installation of a hanging steel structure
  • A construction method for reverse installation of a hanging steel structure
  • A construction method for reverse installation of a hanging steel structure

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0039] Embodiments of the present invention are described below through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific implementation modes, and various modifications or changes can be made to the details in this specification based on different viewpoints and applications without departing from the spirit of the present invention.

[0040] The invention is suitable for the construction of multi-layer super-high hanging steel structures with large span, high lower support height, fewer working faces and high installation accuracy requirements, and has the advantages of using BIM simulation analysis, super high support, and reverse three-dimensional intersection construction Features, can pre-analyze and deal with problems, ensure construction quality, reduce costs,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an inverted mounting and constructing method for a hanging type steel structure. The inverted mounting and constructing method for the hanging type steel structure comprises the following steps: arranging an embedded structure of the hanging type steel structure in a process of constructing a main body concrete structure of the hanging type steel structure; erecting a temporary supporting structure in the constructed main body concrete structure; and constructing a temporary supporting surface at a position below a main steel beam of the hanging steel structure; assembling a main steel beam and a hanging pillar; hoisting the main steel beam and the hanging pillar which are assembled to the temporary supporting surface, and fixing an end of the main steel beam with the embedded structure; hoisting the hanging type steel structure layer by layer from top to bottom at a position below the main steel beam and the hanging pillar, and fixing the end of the hanging type steel structure by the embedded structure after the different layers of the hanging type steel structure is hoisted in place; finishing hoisting and fixing of all the layers of the hanging steel structure; and disassembling the temporary supporting structure. BIM simulation analysis, ultra-high supporting and inverted vertical crossing construction are implemented, problems can be pre-analyzed and treated, construction quality is guaranteed, the costs are reduced, and the construction period is shortened.

Description

technical field [0001] The invention relates to the construction field of steel structure building systems, in particular to a method for reverse installation and construction of a bottom-hanging steel structure. Background technique [0002] With the development of the national economy and the diversification of architectural design, more and more space special-shaped steel truss structures are used in various large-scale stadium buildings. It has been developed from the ground to be installed on the roof of the concrete building, and it is cross-constructed with other professions. The space available for hoisting is very small, and the conventional hoisting process cannot solve such problems. [0003] At present, during the construction of steel truss structure buildings, it is difficult to lift the steel truss from bottom to top. Under the condition of narrow space, it cannot be hoisted directly on the reinforced concrete structure floor, and the arc-shaped main truss is ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/14
CPCE04G21/14
Inventor 黄贵王维高宗立莫凡戴修成陈法兵丁伟陈宏谋
Owner CHINA CONSTR EIGHT ENG DIV CORP LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products