Manufacturing process of particle collecting structure
A particle capture and manufacturing process technology, applied in the field of particle traps, can solve the problems of high processing cost, difficult processing, lack of structural processing devices, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] refer to figure 1 , figure 2 , image 3 As shown, a particle trapping structure, the body of which is a wave plate 1 with a corrugated cross-section, and a plurality of blocking structures 4 are evenly arranged on the longitudinal crests and troughs, and are integrally formed on the wave plate 1, Its production process includes:
[0030] a) Corrugation: roll the metal flat plate into a corrugated plate by rolling the pressure pulsator 10, 11 up and down;
[0031] b) Cutting wave crests and troughs: use the upper circular blade 20 to roll and cut the wave crests of the wave board to form gaps, and at the same time, use the lower circular blade 21 to roll and cut the wave troughs to form gaps, and the gaps on the wave peaks and wave troughs are evenly staggered vertically;
[0032] c) Forming the blocking structure: the wave board that has completed step b is formed into the blocking structure 4 by rolling the arc pressure heads 30 and 31 up and down in a unified dire...
Embodiment 2
[0035] refer to Figure 4 As shown, by merging the tooling in step a and step b in embodiment 1, the upper and lower circular blades 20, 21 in step b are correspondingly installed on the tooling in step a, and the upper and lower rolling pressure pulsators 10, 11 Up, refit into rolling pressure pulsators 12 and 13 with upper and lower circular blades, and then roll the metal flat plate to form a wave plate with gaps, and finally follow step c in Example 1 to form particles capture structure.
[0036] Through the combination of tooling, one process can be saved in the manufacturing process of the particle trapping structure, and the processing cost can be reduced at the same time.
Embodiment 3
[0038] refer to Figure 5 As shown, by merging the tooling in step a, step b and step c in embodiment 1, the circular blade in step b is correspondingly installed on the tooling in step a, on the rolling pressure pulsator 10, 11, and then The arc pressure head 32 of step c is uniformly installed on the groove of the upper and lower rolling pressure pulsators and one side of the circular blade, and is refitted as the upper and next forming pressure pulsators 14, 15, and then the metal plate is rolled. The particle trapping structure can be molded at one time.
[0039] Through the combination of tooling, the particle trapping structure is formed at one time, the process is simple, the operation is convenient, and the processing cost is greatly reduced.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com