UPS steady state test method
A test method, steady state technology, applied in the field of UPS steady state test, can solve problems such as lack of efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0013] The present invention will be described in further detail below.
[0014] Under normal conditions, the test is carried out under no load, 50% rated load and 100% rated load. Specifically include the following steps:
[0015] Test waveform:
[0016] In the no-load and full-load states, observe whether the waveform is normal, and use a distortion measuring instrument to measure the distortion of the output voltage waveform. Under normal working conditions, connect a resistive load and use a distortion meter to measure the relative content of the total harmonics of the output voltage waveform, which should meet the requirements specified by the product, generally less than 5%.
[0017] Test frequency:
[0018] The frequency of the output voltage can be observed with an oscilloscope and measured with a "power disturbance analyzer". When the accuracy of the UPS output frequency is synchronized with the alternating current, it can reach ±0.2%.
[0019] Test output voltag...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com