Construction method of pipe pile foundation for bottom mud treatment plant
A construction method and technology of a treatment plant, applied in the direction of basic structure engineering, construction, etc., can solve the problems of large impact on the quality of structural mechanical properties, long construction period, and heavy on-site labor, so as to shorten the construction period, achieve good quality, and improve construction quality. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0028] A sediment treatment plant is located in a southern city, and the current area is a pond. The total area of the pond is about 82,000 m 2 , the sediment treatment plant covers an area of about 25,500 m 2 . The foundation is heavily loaded by the superstructure and the foundation soil cannot be directly used as a bearing layer. Therefore, pretensioned prestressed high-strength concrete pipe piles (PC piles) are used to reinforce the foundation, including the dehydration workshop in the sediment treatment plant and the gas storage tank pipes. The two areas of the pile foundation project are also an important part of the sediment treatment plant.
[0029] According to the existing survey data, comprehensive regional data and on-site geological survey, there are Quaternary artificial fill layers (Q ml ), Quaternary alluvium (Q al ), Jurassic sedimentary rock (J) argillaceous siltstone, according to its origin and material composition, can be divided into 5 engineering...
Embodiment 2
[0063] A method for constructing a pipe pile foundation for a bottom sludge treatment plant, comprising the following steps:
[0064] (1) Site leveling: clean up various wastes in the pile foundation area, then backfill the foundation to the design elevation, carry out earthwork balance, and level the site to the pile foundation construction requirements;
[0065] (2) On-site setting-out: set multiple control pile pre-leveling points near the piling construction area, and the axis control should be set at a distance of 7-8m from the outer pile to control the axis and elevation of the pile; place the pile positioning line according to the drawing , press outward from the center to form piles to prevent leaks and dislocations; according to the known control points on site, the pile position control points are measured and released according to the pile spacing required by the design;
[0066] (3) Pile driving equipment preparation: move the pile driver to the pile position accor...
Embodiment 3
[0096] A method for constructing a pipe pile foundation for a bottom sludge treatment plant, comprising the following steps:
[0097] (1) Site leveling: clean up various wastes in the pile foundation area, then backfill the foundation to the design elevation, carry out earthwork balance, and level the site to the pile foundation construction requirements;
[0098] (2) On-site setting-out: set multiple control pile pre-leveling points near the piling construction area, and the axis control should be set at a distance of 7-8m from the outer pile to control the axis and elevation of the pile; place the pile positioning line according to the drawing , press outward from the center to form piles to prevent leaks and dislocations; according to the known control points on site, the pile position control points are measured and released according to the pile spacing required by the design;
[0099] (3) Pile driving equipment preparation: move the pile driver to the pile position accor...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com