A construction technology and waterproof membrane technology, which is applied in the direction of building components, coatings, building insulation materials, etc., can solve the problems of waterproof system leakage, affecting the quality of buildings, etc., to achieve easy maintenance, shorten the construction period, and easy construction Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0059] A construction technique for a zero-leakage waterproof system, comprising the following steps:
[0060] Step 1: Base Cleanup
[0061] Clean up the sand and dust on the outer surface of the base;
[0062] Step 2: Apply base treatment agent
[0063]Apply the prepared treatment agent to the cleaned outer surface of the base;
[0064] The treatment agent comprises the following components in parts by weight:
[0065] 20 parts of asphalt 70#; 1 part of oleic acid; 2 parts of caustic soda; 3 parts of OP-10; 2 parts of water glass; 1.5 parts of PVA;
[0066] Step 3: Detail node processing
[0067] Viscose composite mesh cloth is used for treatment at the yin and yang corners, water outlets, and roof structures;
[0068] Step 4: Trial laying of waterproof membrane
[0069] Unfold the waterproof membrane on the base layer, and roll it back after determining the position;
[0070] The waterproof membrane includes the following components in parts by weight: 58 parts of asp...
Embodiment 2
[0080] A construction technique for a zero-leakage waterproof system, comprising the following steps:
[0081] Step 1: Base Cleanup
[0082] Clean up the sand and dust on the outer surface of the base;
[0083] Step 2: Apply base treatment agent
[0084] Apply the prepared treatment agent to the cleaned outer surface of the base;
[0085] The treatment agent comprises the following components in parts by weight:
[0086] Wherein, the treating agent comprises the following components in parts by weight:
[0087] 35 parts of asphalt 70#; 1.5 parts of oleic acid; 2.5 parts of caustic soda; 3.2 parts of OP-10; 2.5 parts of water glass; 1.7 parts of PVA;
[0088] Step 3: Detail node processing
[0089] Viscose composite mesh cloth is used for treatment at the yin and yang corners, water outlets, and roof structures;
[0090] Step 4: Trial laying of waterproof membrane
[0091] Unfold the waterproof membrane on the base layer, and roll it back after determining the position; ...
Embodiment 3
[0102] A construction technique for a zero-leakage waterproof system, comprising the following steps:
[0103] Step 1: Base Cleanup
[0104] Clean up the sand and dust on the outer surface of the base;
[0105] Step 2: Apply base treatment agent
[0106] Apply the prepared treatment agent to the cleaned outer surface of the base;
[0107] The treatment agent comprises the following components in parts by weight:
[0108] The treatment agent described in step 2 comprises the following components in parts by weight:
[0109] 50 parts of asphalt 70#; 2 parts of oleic acid; 3 parts of caustic soda; 3.5 parts of OP-10; 3 parts of water glass; 2 parts of PVA;
[0110] Step 3: Detail node processing
[0111] Viscose composite mesh cloth is used for treatment at the yin and yang corners, water outlets, and roof structures;
[0112] Step 4: Trial laying of waterproof membrane
[0113] Unfold the waterproof membrane on the base layer, and roll it back after determining the positi...
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com