Continuous prefabricated asphalt pavement and construction method thereof
A technology of asphalt pavement and construction method, which is applied to the pavement paved with prefabricated blocks, manufacturing tools, roads, etc., can solve the problems of reflective crack construction efficiency, etc., and achieve the effects of avoiding traffic congestion, ensuring construction quality, and ensuring construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach 1
[0030] Embodiment 1: The continuous prefabricated asphalt pavement in this embodiment is composed of a prefabricated asphalt pavement slab, an upper layer 6, a cushion layer 7 and a soil foundation 8;
[0031] The cushion layer 7 is arranged on the upper surface of the soil foundation 8, the prefabricated asphalt road slab is arranged on the upper surface of the cushion layer 7, and the upper layer 6 is arranged on the upper surface of the prefabricated asphalt road slab and bonded by an emulsified asphalt adhesive;
[0032] The prefabricated asphalt road slab is composed of a plurality of prefabricated slab units; the prefabricated slab unit is composed of a base layer 1, a lower layer 2 and a middle layer 3; the lower layer 2 is arranged on the upper surface of the base layer 1 and bonded by an emulsified asphalt adhesive , the side of the lower layer 2 is set on the inner side of the side of the base layer 1, the middle layer 3 is set on the upper surface of the lower layer ...
specific Embodiment approach 2
[0037] Specific Embodiment 2: The difference between this embodiment and Specific Embodiment 1 is that the double-tenon coupling block is composed of two tenons 5 with the same shape and matched with the tenon groove 4. One end of the tenon 5 is a larger end surface, and the other end is The smaller ends of the two mortises 5 are relatively fixed. Other steps and parameters are the same as those in the first embodiment.
specific Embodiment approach 3
[0038] Embodiment 3: This embodiment differs from Embodiment 1 or Embodiment 2 in that: the tenon groove 4 is a trapezoidal groove, and the smaller bottom side of the tenon groove 4 is an opening. Other steps and parameters are the same as those in the first embodiment.
PUM
Property | Measurement | Unit |
---|---|---|
compressive strength | aaaaa | aaaaa |
particle diameter | aaaaa | aaaaa |
flexural strength | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com