A method for prolonging the gas recovery time by shutting down the blast furnace empty material line
A technology of empty material line and gas, which is applied in the field of control of blast furnace shutdown to draw water and empty material line, and the field of blast furnace empty material line shutdown to prolong the time of gas recovery, which can solve the problems of long air pollution time and extend the recovery time of gas The effect of stable pressure and obvious social benefits
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047] This embodiment provides a method for shutting down the blast furnace empty material line to prolong the recovery time of gas, which specifically includes the following steps:
[0048] (1) Install blast furnace top atomization water pumping system before shutdown, and use it normally
[0049] Install the furnace top atomization water pumping system before the shutdown of the furnace. The specific requirements of the water pumping system: ①The number of spray guns should reach at least 8; ②The water sprayed by the spray guns should have a good atomization effect, and the atomized water particles should be less than 500 μm;
[0050] (2) One day before the shutdown, adjust the composition of slag and iron and the temperature of molten iron
[0051] According to the current production situation, reduce the coke load, control the coal ratio to less than 100kg / t, add serpentine, limestone, silica, and fluorite to adjust the composition of slag and iron to ensure good fluidity...
Embodiment 2
[0071] This example provides a specific embodiment of the method of shutting down the blast furnace empty material line to prolong the recovery time of gas, using 2150m 3 blast furnace for testing;
[0072] (1) Install blast furnace top atomization water pumping system before shutdown, and use it normally
[0073] From July 12th to 14th, the blast furnace was scheduled to be repaired for 48 hours. Taking this opportunity, the original furnace top cooling sprinkler system was transformed into a furnace top atomization water pumping cooling system, and the original four water pipes on the furnace top were cut off and placed on the same level. Opened 4 new holes, purchased and installed 8 single-fluid automatic telescopic atomizing anti-blocking spray guns and water pipes, control systems, etc. on the market, and the furnace top spray water cooling system was connected to the original blast furnace top sprinkling main pipe, and the original blast furnace The top sprinkling main ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com