Method for constructing composite lightweight batten walls

A construction method and technology of slab walls, applied to walls, building components, buildings, etc., can solve the problems of complex construction process, low construction quality and efficiency, and achieve the effect of simple process, high construction efficiency and not easy to crack

Inactive Publication Date: 2018-12-28
SHANGHAI BAOYE GRP CORP
View PDF4 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] Prefabricated grouting wall, also known as double-check sandwich energy-saving wallboard, is made of single-layer double-sided cement fiberboard fixed by shaping abrasives, filled with EPS polystyrene foam particle concrete, prefabricated by vibrating and curing, and then assembled and fixed. The formed wall, the review lightweight strip wall is a kind of prefabricated grouted wall, which is widely used because of its light weight and obvious advantages in heat preservation, water break, fire prevention and air tightness, but the existing review lightweight strip The construction process of the board wall is complicated, and the construction quality and efficiency are low

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] The present invention will be further described below in conjunction with specific examples, so that those skilled in the art can better understand the present invention and implement it, but the given examples are not intended to limit the present invention.

[0021] This embodiment discloses a construction method for reviewing lightweight slatted walls. The reviewing lightweight slatted wall includes a plurality of wallboards. During construction, first clean the structural base, then perform positioning and laying out, and then perform the following steps:

[0022] 1) Apply mortar to the edge of the wall panel; for example, apply mortar to the edge where the wall panel needs to be connected with other wall panels, beams or columns;

[0023] 2) Move the multiple wall panels that have been coated with mortar to the assembly position for assembly; the joint width of adjacent wall panels is 10mm;

[0024] 3) Use the crowbar to correct the position of the wall panel, and ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
widthaaaaaaaaaa
lengthaaaaaaaaaa
Login to view more

Abstract

The invention discloses a method for constructing composite lightweight batten walls. The composite lightweight batten walls comprise a plurality of wallboards. The method includes steps of smearing mortar at the edges of the wallboards; shifting the multiple wallboards with the smeared mortar to assembling locations and assembling the wallboards; tilting the wallboards by the aid of prying rollers until the mortar is squeezed from the tops of the wallboards and then filling spaces between the wallboards and the ground with wooden wedges; knocking steel nails in spaces between every two adjacent wallboards in oblique downward directions; fixing the wallboards and beams by the aid of connecting reinforcing steel bars, fixing the wallboards and columns by the aid of connecting reinforcing steel bars, filling assembly seams between the wallboards and the beams with mortar, and filling assembly seams between the wallboards and the columns with mortar; taking out the wooden wedges after therequirements on the strength of the mortar are met, and then fully filling gaps between the wallboards and the ground with mortar; sealing board joints between the various wallboards by anti-crackingstrips and then troweling the board joints by mortar. The method has the advantages that the method includes simple processes, and the construction quality and efficiency can be effectively improved.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to a construction method for double-checking lightweight slat walls. Background technique [0002] Prefabricated grouting wall, also known as double-check sandwich energy-saving wallboard, is made of single-layer double-sided cement fiberboard fixed by shaping abrasives, filled with EPS polystyrene foam particle concrete, prefabricated by vibrating and curing, and then assembled and fixed. The formed wall, the double-check lightweight strip wall is a kind of prefabricated grouted wall, which is widely used because of its light weight and obvious advantages in heat preservation, water break, fire prevention and air tightness, but the existing double-check light strip The construction process of the board wall is complicated, and the construction quality and efficiency are low. Contents of the invention [0003] The technical problem to be solved by the present invent...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04B2/86
CPCE04B2/86
Inventor 江华龚锦
Owner SHANGHAI BAOYE GRP CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products