Pre-splitting blasting construction method for shield tunneling in upper soft and lower hard strata

A pre-splitting blasting and construction method technology, which is applied in blasting, earthwork drilling, mining equipment, etc., can solve problems such as increased construction risk, fast hob wear, and tunneling tool wear, so as to save shield construction costs and solve The effect of solving technical problems and improving tunneling efficiency

Active Publication Date: 2018-12-14
CHINA RAILWAY 16 BUREAU GRP BEIJING METRO ENG CONSTR +1
View PDF5 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The construction of the shield method in the upper soft and lower hard geological layers is likely to cause some problems: for example: 1. In this type of stratum, the excavation efficiency is low, the cutterhead and cutter wear are serious, and it is easy to cause cutter jamming, inclined cutter, cutter drop, and partial wear of the cutter, etc. , the processing speed is relatively slow, seriously affecting the construction progress, and some even have to change the design because the construction cannot progress, the cost is high, and the economic benefit is poor; The problem of ground subsidence has a huge impact on the surrounding environment, and it will also cause serious wear and tear on the excavation tools
3. In the hard rock section, not only the excavation side hob wears quickly, but also the shield machine is prone to jamming. Therefore, frequent tool opening inspections are required, which increases the construction risk; 4. The soft and hard geological strata are in the lower The slope section has a certain negative impact on the excavation construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Pre-splitting blasting construction method for shield tunneling in upper soft and lower hard strata
  • Pre-splitting blasting construction method for shield tunneling in upper soft and lower hard strata
  • Pre-splitting blasting construction method for shield tunneling in upper soft and lower hard strata

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0065] Taking the section between the newly built Zhuhai urban area and Zhuhai Airport Intercity Rail Transit Project Phase 1 #1-Wanzai North Station section as an example, a shield excavation method for pre-splitting blasting in the upper soft and lower hard strata is introduced, including the following sequential steps (see Figure 9 Schematic flow chart of the pre-splitting blasting construction method for shield excavation in upper soft and lower hard strata):

[0066] Step S1: First, survey the unfavorable geological sections within the excavation range (that is, the section where the upper soil is soft and the lower soil is hard) before shield excavation to determine the specific areas of the upper soft and lower hard strata, and then according to the survey results The specific area and distribution form of the upper soft and lower hard unfavorable geological sections determine the pre-splitting blasting area;

[0067] Step S2: According to the determined blasting area,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Densityaaaaaaaaaa
Diameteraaaaaaaaaa
Particle sizeaaaaaaaaaa
Login to View More

Abstract

The invention discloses a pre-splitting blasting construction method for shield tunneling in upper soft and lower hard strata. The pre-splitting blasting construction method for shield tunneling in the upper soft and lower hard strata comprises the following steps that according to a determined blasting area, pre-splitting blasting hole arrangement is carried out, specifically, hole arrangement forms of blasting holes, auxiliary holes and shock absorption holes are included, and drilling construction is carried out after the hole arrangement is qualified through acceptance; after the drillingis completed, the explosive quantity calculation and charge processing are carried out, then a charge structure is determined and the initiation network is designed; anti-floating counterweight of explosive, charge emplacement and protection are carried out, then initiation is carried out, and the blasting effect is tested after completion of blasting; after the blasting construction is completed,the remaining holes are sealed and blocked to avoid slurry leakage when a shield passes through the blasting area, and after the hole sealing is completed, shield tunneling is carried out. The pre-splitting blasting construction method greatly saves the construction cost of the shield and can effectively solve the technical problem of processing boulders and hard rock sections encountered in shield tunneling by adopting the pre-splitting blasting technology for the sections.

Description

technical field [0001] The invention relates to the technical field of tunnel engineering blasting by shield tunneling method, in particular to a construction method for pre-splitting blasting in upper soft and lower hard strata for shield excavation. Background technique [0002] In recent years, with the rapid development of urban rail transit construction, more and more cities have begun to build large-scale urban rail transit such as intercity railways. The construction of track sections in most cities adopts shield tunneling method. During the construction process, randomly distributed boulders and bedrock protruding upper soft and lower hard strata are often encountered, and the boulders have different shapes and sizes and different strengths, and the hard rock has extremely high strength. [0003] The construction of the shield method in the upper soft and lower hard geological layers is likely to cause some problems: for example: 1. In this type of stratum, the excav...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): F42D1/00F42D3/04E21D9/00
CPCE21D9/006F42D1/00F42D3/04
Inventor 黄昌富田书广朱垚锋黄君陶红杰赖力前李景阳张辉陈贺李万春
Owner CHINA RAILWAY 16 BUREAU GRP BEIJING METRO ENG CONSTR
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products