Air film concrete construction mold plate construction technology
A construction technology and concrete technology, applied in construction, building construction, etc., can solve problems such as large consumption of materials and manpower, affecting project quality, deformation of wooden formwork, etc., to achieve high space utilization, simple construction technology, saving occupation. land area effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0025] A kind of air film concrete construction template construction technology, it comprises the following steps:
[0026] 1) Site leveling: site leveling before construction, reinforcement and replacement of soft parts in the site that are not conducive to construction, and regular inspection and review;
[0027] 2) Membrane material cutting: Calculate the membrane material according to the shape of the building to be built and cut it into sheets for later use;
[0028] 3) Construct the foundation ring beam: construct the foundation ring beam according to the actual construction objects, weld the brackets for anchor bolts on the side of the foundation ring beam, then pour concrete on the foundation ring beam, and maintain for 10 days after pouring;
[0029] Wherein, the pouring adopts cement mortar for slope layered pouring, and the layered thickness of the pouring is 300mm, and the slope is 1:7; in step 3), the curing is to pave a layer on the surface after the concrete po...
Embodiment 2
[0036] A kind of air film concrete construction template construction technology, it comprises the following steps:
[0037] 1) Site leveling: site leveling before construction, reinforcement and replacement of soft parts in the site that are not conducive to construction, and regular inspection and review;
[0038] 2) Membrane material cutting: Calculate the membrane material according to the shape of the building to be built and cut it into sheets for later use;
[0039] 3) Construct the foundation ring beam: Construct the foundation ring beam according to the actual construction object, weld the brackets for anchor bolts on the side of the foundation ring beam, then pour concrete on the foundation ring beam, and maintain it for 20 days after pouring;
[0040] Wherein, the pouring adopts cement mortar for slope layered pouring, and the layered thickness of the pouring is 300mm, and the slope is 1:7; in step 3), the curing is to pave a layer on the surface after the concrete ...
Embodiment 3
[0047] A kind of air film concrete construction template construction technology, it comprises the following steps:
[0048] 1) Site leveling: site leveling before construction, reinforcement and replacement of soft parts in the site that are not conducive to construction, and regular inspection and review;
[0049] 2) Membrane material cutting: Calculate the membrane material according to the shape of the building to be built and cut it into sheets for later use;
[0050] 3) Construct the foundation ring beam: construct the foundation ring beam according to the actual construction object, weld the brackets for anchor bolts on the side of the foundation ring beam, then pour concrete on the foundation ring beam, and maintain it for 15 days after pouring;
[0051] Wherein, the pouring adopts cement mortar for slope layered pouring, and the layered thickness of the pouring is 300mm, and the slope is 1:7; in step 3), the curing is to pave a layer on the surface after the concrete ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com