Combined pile foundation structure suitable for coral reef geology and construction method of structure
A technology of combined piles and coral reefs, which is applied in the direction of foundation structure engineering, sheet pile walls, buildings, etc., can solve the problems of reducing the bearing capacity of foundation piles, self-heavy weight, and multiple voids, and achieve the goal of reducing the design length and the self-weight of pile foundations Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0036] Such as figure 1 As shown, the present invention provides a kind of combined pile foundation structure suitable for coral reef geology, comprising:
[0037] The lower end of the prestressed pipe pile 1 is inserted into the coral reef rock and soil, and the cast-in-situ pile 2 is arranged in the lower section; the prestressed pipe pile is a UHPC pipe pile. The prestressed pipe pile 1 is driven into a certain depth to maintain its own balance, and the prestressed pipe pile 1 is used as a casing to directly perform conventional auger drilling operations in the hole. The prestressed pipe pile 1 can balance the water pressure, prevent the hole from collapsing, and at the same time isolate the surface water, protect the ground of the hole, fix the position of the pile foundation and guide the drill bit, etc.; The prestressed pipe pile 1 is fixed, which not only has a better stabilization effect, but also has less damage to the coral reef sandstone under the same strength, an...
Embodiment 2
[0039] In another embodiment, as figure 2 As shown, the described combined pile foundation structure suitable for coral reef geology also includes:
[0040]steel pipe column 3, which is located above the prestressed pipe pile 1, and is sleeved outside the prestressed pipe pile 1 with a certain distance to form an annular hollow grouting space 4, and the two are partially overlapped and sleeved, The hollow grouting space in the overlapping part is filled with grouting materials; the upper part of the steel pipe column is exposed to rock and soil for connection with the external structure; the inner wall of the steel pipe column is uneven to form concave-convex shear teeth. The temporary support bracket 5 is vertically connected to the prestressed pipe pile 1 and is arranged around the prestressed pipe pile in the circumferential direction. The temporary support bracket 5 is closely attached to the lower end of the steel pipe column 3 to The steel pipe column 3 plays a role of...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com