Operation method for performing quick grouting on curtain
An operation method and fast technology, applied in construction, sheet pile walls, foundation structure engineering, etc., can solve problems such as poor grouting quality, unsatisfactory construction requirements, complicated curtain grouting process, etc., to improve grouting efficiency and meet construction requirements Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0030] The operation method of quickly grouting the curtain is characterized in that it comprises the following steps:
[0031] (1) Construction survey: Before construction, according to the measurement reference point, reference line and its reference data and data provided by the supervision department, check the measurement accuracy of the reference point or line, and review the accuracy of the data and data, according to the provided Measurement data, actual measurement of the axis of the curtain grouting hole;
[0032] (2) Arrangement of grouting holes: Arrange grouting holes on the axis of the cut-off wall according to the design requirements, divided into sequence III, the hole distance is 2m, the axial deviation of the hole position shall not exceed 10cm, and the hole depth is 10m at the bottom of the cut-off wall concrete;
[0033] (3) Drilling: Grouting deep holes, core holes and inspection holes are drilled with a drilling rig with a diameter of 91mm, drilled with a...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com