Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method of deep-water foundation with long-span continuous beam adjacent to existing line

A deep-water foundation and construction method technology, applied in the direction of foundation structure engineering, building, sheet pile wall, etc., can solve the problems of random construction operation, complicated construction procedures, poor construction effect, etc., and achieve low construction cost, low input cost, The effect of easy processing and production

Active Publication Date: 2020-07-28
CHINA RAILWAY 20 BUREAU GRP CORP LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

When the underwater blasting method is used to excavate the underwater foundation pit of the above-mentioned deep-water foundation of the bridge near the existing line, since the Yongjiang River is currently a Class III navigable channel, and the excavated foundation pit is relatively close to the existing bridge, if the underwater foundation pit is selected For excavation by blasting method, firstly, it is necessary to temporarily block the waterway, and secondly, it is necessary to go through the construction procedures near the existing line, and carry out blasting operations in the "blockade point". At the same time, it is also necessary to consider the impact of blasting on existing bridges, and the The selection of post-slag cleaning equipment requires a large cost investment, and more importantly, the construction procedures are very complicated
However, at present, when using the mechanical crushing method to excavate the underwater foundation pit of the bridge deep water foundation near the existing line, there is no unified, standard and standardized construction method to follow. During the construction process, the construction operation is inevitably relatively random, Problems such as low construction efficiency and poor construction effect

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of deep-water foundation with long-span continuous beam adjacent to existing line
  • Construction method of deep-water foundation with long-span continuous beam adjacent to existing line
  • Construction method of deep-water foundation with long-span continuous beam adjacent to existing line

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0078] Such as figure 1 A deep-water foundation construction method for long-span continuous beams close to the existing line is shown. The deep-water foundation to be constructed includes a water cap on the underwater bedrock on one side of the existing railway operation line and multiple roots for the water cap. For the supported bored piles, a plurality of the bored piles are all located under the water cap, and the plurality of the bored piles are arranged vertically and are all located on the same horizontal plane. The water cap is adopted The concrete cap of cofferdam 14 construction molding; When carrying out construction to described water cap, comprise the following steps:

[0079] Step 1. Excavation of underwater foundation pit: if Picture 1-1 As shown, the underwater foundation pit installed at the bottom of the cofferdam 14 is excavated, and the process is as follows:

[0080] Step 101, erecting the excavation platform: erecting the excavation platform;

[0081...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a deep-water foundation construction method for a large-span continuous beam adjacent to an existing railway line. A deep-water foundation for construction comprises an underwater abutment and a plurality of drilled piles, wherein the underwater abutment is positioned on an underwater base rock on one side of the existing operating railway line, and the drilled piles are used for supporting the underwater abutment. The deep-water foundation construction method includes the steps: firstly, excavating an underwater foundation pit mounted at the bottom of a cofferdam by setting up an excavation platform, mounting an impact drill, moving the excavation platform and performing first impact, synchronous slag removal, second impact and synchronous slag removal; secondly, constructing the drilled piles and the underwater abutment by surveying and setting out, lowering a cofferdam, mounting a steel casing, sealing the bottom of the cofferdam, constructing the drilled piles, drawing water in the cofferdam, cutting off the steel casing and constructing the abutment. The steps are simple, the method is reasonable in design, simple and convenient in construction, good in use effect, safe and reliable in construction process and less in external influence, and the deep-water foundation construction process can be simply, conveniently and rapidly finished.

Description

technical field [0001] The invention belongs to the technical field of bridge construction, and in particular relates to a deep-water foundation construction method of a long-span continuous beam adjacent to an existing line. Background technique [0002] At present, my country's railway bridge construction is in a period of rapid development, and the use of advanced design and construction technology to achieve the goal of saving investment, shortening the construction period, and ensuring safety has always been the result pursued by the engineering community. Among them, in the construction of long-span and deep-water bridges, the design theory, construction technology and equipment have reached or approached the world's advanced level. For example, in the continuous girder construction of the new second-line new Yongjiang Bridge in Nanning Railway Hub, the main span of the bridge reaches 168m, which is the largest span among single-line railway bridges in China. The cons...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D27/14E02D5/40E02D19/04
CPCE02D5/40E02D19/04E02D27/14E02D2250/0061
Inventor 仲维玲丁大有李洁勇王克俭
Owner CHINA RAILWAY 20 BUREAU GRP CORP LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products