A Novel Delayed Coking Method
A delayed coking and coking tower technology, applied in the field of delayed coking technology, can solve the problems of easy coking and clogging of filling pipelines, low use efficiency, etc., and achieve the effects of reducing entrainment, improving use efficiency and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0031] The defoamer is prepared from the following raw materials in parts by mass: 10 parts of polyborosiloxane, 20 parts of ethyl cellulose, 10 parts of ultra-high viscosity linear polydimethylsiloxane, iron-based polysilicon 2 parts of azane, 20 parts of cetyl alcohol, 38 parts of coker wax oil. After mixing the above raw materials, stir at 60° C. for 2 hours, and then obtain a defoamer product of the present invention after cooling.
Embodiment 2
[0033] Coking raw materials are imported from the Middle East to reduce slag, and the properties are as follows: Density (20°C) is about 989.76kg / m 3, the sulfur content is 2.62% (m / m), the carbon residue is 23.35% (m / m), and the contents of the four components are 14% saturated hydrocarbons, 36.4% aromatics, 34.6% colloids, and 15% asphaltenes. The processing capacity of the industrial device is 160 tons / hour, the production cycle is 24 hours, the circulation ratio is 0.13, the outlet temperature of the heating furnace is 490°C, the oil and gas outlet temperature at the top of the coke tower is 421°C, and the pressure at the top of the tower is 0.16MPa.
[0034] Adopt the antifoaming agent filling method described in the present invention, adopt the antifoaming agent that embodiment 1 obtains. The specific structure of the selected two-fluid nozzle is as follows: the circular diameter of the center liquid nozzle is 16mm, the diameter of the gas ring pipe is 22mm, and the exit...
Embodiment 3
[0036] Same as Example 1, except that the temperature of the circulating compressed dry gas is 180° C., and the flow rate of the defoamer is 22 L / hour. Starting from the moment when the neutron material level meter first shows that it rises to 10%, inject the defoamer until half an hour after the tower is cut, stop injecting the defoamer. The total filling time of the defoamer in this cycle is about 5.5 hours, the total consumption of the defoamer is about 121L, and the unit consumption in a single cycle is about 26.36ppm. Usually in production, the defoaming time (the time interval between the neutron level meter showing twice before and after rising to 10%) is used as the standard for evaluating the defoamer effect. The defoaming time in this production cycle is 2.6 hours, and the corresponding coking gas , Diesel sampling analysis, silicon content in coked gasoline is about 1.48ppm, no silicon residue was detected in coked diesel.
PUM
Property | Measurement | Unit |
---|---|---|
kinematic viscosity | aaaaa | aaaaa |
kinematic viscosity | aaaaa | aaaaa |
kinematic viscosity | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com