Construction method of prestress common pipe ditch

A construction method and common management technology, applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve problems such as large hidden dangers of water leakage, large steel consumption, and troublesome construction process.

Active Publication Date: 2014-11-26
ZHONGKE SUNBROAD CONSTR GRP CO LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The construction joints are prone to water leakage, so a ring of water-stop steel plates is pre-embedded in the concrete at the construction joints. However, due to too many construction joints, the hidden danger of water leakage is still relatively large; moreover, it needs to consume a large amount of water-stop steel plates, and the steel consumption is large; moreover, Each time the prestressed steel bars of a first-cast pipe section are stretched, the non-prestressed steel bars anchored with the first-cast pipe section and the next first-cast pipe section at the same time need to be cut before tensioning. The reconnection of non-prestressed steel bars, the construction process is quite troublesome

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of prestress common pipe ditch
  • Construction method of prestress common pipe ditch
  • Construction method of prestress common pipe ditch

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0035] Such as figure 1 , figure 2 , image 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 The construction method of the prestressed common trench of the present invention shown, it comprises the following steps.

[0036] a. Excavate the trench 1 for accommodating the prestressed common pipe trench.

[0037] b. Bind and fix the hoop-direction steel bars and the longitudinal or length-wise steel bars and lay the formwork. The longitudinal steel bars include non-prestressed steel bars and prestressed steel bars 2. Wherein, the rear ends of prestressed steel bars 2 in odd sections are warped outward, and the front ends of prestressed steel bars 2 in even sections are warped outwardly, and a sleeve is fixed to the warped end 2.1 of each prestressed steel bar 2 . There is a ring of water-stop steel plates 3 between the prestressed steel...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a prestress common pipe ditch, which comprises the following steps of: a, excavating a groove; b, binding and fixing circular reinforcing steel bars and longitudinal reinforcing steel bars and laying a template; c, pouring several sections of concrete pipelines (4) in section from front to back; d, drawing out sleeves of outside warped ends (2.1) of all prestress reinforcing steel bars (2) to form a tensioning groove (6) corresponding to the outside warped end (2.1) of each prestress reinforcing steel bar (2) one by one which is reserved on each section of concrete pipe (4); e, tensioning the outside warped end (2.1) of the prestress reinforcing steel bar (2) in each tensioning groove (6) and anchoring with an anchorage device (7) on each tensioning end; and f, filling and floating each tensioning groove (6) with fine aggregate concrete. The construction method can reduce leakage hidden trouble, saves steels and has convenient construction process.

Description

technical field [0001] The invention relates to the field of municipal underground structures, in particular to a construction method for a prestressed common pipe ditch. Background technique [0002] With the rapid development of the national economy, the application range of prestressed common trenches under municipal roads is becoming more and more extensive. The prestressed common pipe trench is a square tube of prestressed reinforced concrete structure buried underground and extending along the length direction. Power pipelines, gas pipes, water pipes and heating pipes, etc., the prestressed common pipe trench makes the distribution of the above pipelines neat and reasonable, and is convenient for maintenance. [0003] The construction method of the prestressed common trench in the prior art includes the following steps. [0004] a. Excavate the trench to accommodate the common prestressed pipe trench. [0005] b. Bind and fix the steel bars in the circumferential di...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
Inventor 张国庆郑定芳
Owner ZHONGKE SUNBROAD CONSTR GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products