An ancient building and roof ridge technology, which is applied in the field of ancient building roof maintenance, can solve the problems of failure to protect the roof ridge, roof ridge damage, joint collapse, etc., and achieve low production costs, simple components and on-site construction operations, and short construction period Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0015] Taking the overall hoisting of the roof ridge of an ancient building as an example, as shown in Fig. 1 and Fig. 2, the hoisting device 7 of this embodiment adopts a fine-tuning screw. The overall hoisting steps of the main ridge of the roof of the ancient building are as follows: firstly, the roof tiles are disassembled, and a row of vertical steel pipes 1 is established on both sides of the main ridge. Fixed, two rows of vertical steel pipes 1 are connected and fixed with horizontal steel pipes 3 at intervals from bottom to top, each vertical steel pipe 1 is supported and fixed by an oblique steel pipe 4, and the joints of steel pipes and steel pipes are fastened with buttons. The bottom is interspersed with a bottom frame 5, the bottom frame 5 is placed on the horizontal steel pipe 2, clamped with wooden boards on both sides of the main ridge, the board and the main ridge are separated by straw, and long bolts are used to pass through the wooden boards on both sides ,...
Embodiment 2
[0017] Taking the overall hoisting of the vertical ridge of the roof of the ancient building as an example, first remove the roof tiles, follow the method of Example 1 to erect the rod support, select a row of bricks on the wall at the bottom of the vertical ridge, and remove one brick at a certain distance , and then interspersed with a row of backing steel pipes, follow the remaining steps of embodiment 1 to lift the vertical ridge as a whole, after the roof is repaired, lower the vertical ridge back to its original position, re-lay the roof tiles and fill up the bricks.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com