Winter grouting low-consumption construction method for fabricated building
A construction method and prefabricated technology, which is applied in the direction of buildings, building components, building reinforcements, etc., to achieve the effect of benefiting the cost of heat preservation, ensuring the quality of grouting, and ensuring the construction time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] Taking a prefabricated building as an example, the construction period includes winter, and the concrete construction and grouting construction in the industrial construction process are greatly affected by winter construction. It is necessary to make technical preparations and material preparations for winter construction to ensure that the winter construction stage Construction is progressing smoothly. In order to facilitate the characteristics of winter grouting construction, the low-consumption construction method of prefabricated building winter grouting is adopted.
[0044] combine Figure 1 to Figure 3 As shown, a low-consumption grouting construction method for prefabricated buildings in winter. The building is an assembled integral shear wall structure. The prefabricated walls 1 are connected by grouting sleeves 2. The grouting work area is fully enclosed and heat-insulated; low-temperature grouting materials are used for construction. ;
[0045] Step 1. Divi...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com