A technology of ready-mixed concrete and processing methods, applied in the field of ready-mixed concrete construction, can solve problems such as economic loss, impact on concrete durability, service life discount of concrete and engineering structures, etc., to save engineering costs, reduce concrete moisture content, ensure The effect of construction safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0021] Prepare raw materials according to the following parts by weight: gravel 1010, sand 730, cement 330, fly ash 80, water reducing agent 4.0 and water 120;
[0022] Follow the steps below to process:
[0023] S1: Heat the mixing water to 45°C;
[0024] S2: heating gravel and sand to 10°C;
[0025] S3: Insulate cement, fly ash and water reducing agent to ensure that they are used under positive temperature conditions;
[0026] S4: Add the above-mentioned heated and heat-preserved raw materials into a mixer and mix them evenly for 70 seconds;
[0027] S5: Take the mixed concrete out of the machine at 14°C;
[0028] S5: According to the prior art, pump the concrete slurry to the pouring target for the next step of construction.
[0029] The cement is preferably Portland cement, and the fly ash specification adopts F class II with a fineness of 19% and a water demand ratio of 99%. The sand is preferably class II medium sand with a fineness modulus of 2.8 and a mud content ...
Embodiment 2
[0031] Prepare raw materials according to the following parts by weight: gravel 1080, sand 750, cement 345, fly ash 85, water reducing agent 4.3 and water 130;
[0032] Follow the steps below for construction:
[0033] S1: Heat the mixing water to 45°C;
[0034] S2: heating gravel and sand to 10°C;
[0035] S3: Insulate cement, fly ash and water reducing agent to ensure that they are used under positive temperature conditions;
[0036] S4: Add the above-mentioned heated and heat-preserved raw materials into a mixer and mix them evenly for 70 seconds;
[0037] S5: Take the mixed concrete out of the machine at 14°C;
[0038] S5: According to the prior art, pump the concrete slurry to the pouring target for the next step of construction.
Embodiment 3
[0040] Prepare raw materials according to the following parts by weight: gravel 1100, sand 770, cement 370, fly ash 90, water reducing agent 4.5 and water 155;
[0041] Follow the steps below for construction:
[0042] S1: Heat the mixing water to 45°C;
[0043] S2: heating gravel and sand to 10°C;
[0044] S3: Insulate cement, fly ash and water reducing agent to ensure that they are used under positive temperature conditions;
[0045] S4: Add the above-mentioned heated and heat-preserved raw materials into a mixer and mix them evenly for 70 seconds;
[0046] S5: Take the mixed concrete out of the machine at 14°C;
[0047] S5: According to the prior art, pump the concrete slurry to the pouring target for the next step of construction.
PUM
Property | Measurement | Unit |
---|---|---|
slump | aaaaa | aaaaa |
strength | aaaaa | aaaaa |
porosity | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com