Engineering construction progress plan management and control system and method based on BIM model

A technology of schedule planning and model, applied in the field of engineering construction, can solve problems such as rework, incomplete elements, one-sided influencing factors, etc., and achieve the effect of reducing repetitive work and improving execution efficiency

Active Publication Date: 2020-10-09
TIANJIN CEMENT IND DESIGN & RES INST
View PDF5 Cites 12 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] Aiming at the above-mentioned defects of the prior art, the present invention provides a BIM model-based project construction schedule control system and method to solve practical problems such as unreasonable plan generation, incomplete elements, one-sided influencing factors, and rework in the current traditional schedule control , and can effectively achieve the planned revision

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Engineering construction progress plan management and control system and method based on BIM model
  • Engineering construction progress plan management and control system and method based on BIM model
  • Engineering construction progress plan management and control system and method based on BIM model

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0079] The present invention will be further explained below in conjunction with the accompanying drawings and embodiments.

[0080] In this example, a BIM model-based engineering construction schedule control method; used for BIM coding, BIM model control, BIM plan generation, BIM progress feedback, BIM progress simulation and plan revision; see figure 1 , including the following steps:

[0081] S1. Establish a unified BIM coding standard;

[0082] See Table 1. The unified BIM coding standard includes project information, workshop information, business information, professional information, spatial area information, floor information, category information, equipment coding information, etc.

[0083] Table 1 Basic material attributes and product attributes

[0084]

[0085] For a BIM model, a model component code can be expressed as: XXX.002.ER.BA.DB1.1F.PR.PR01

[0086] S2. Establish BIM model

[0087] In the BIM modeling software, the 3D model is built according to pr...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an engineering construction progress plan management and control system and method based on a BIM model. The system and method are used for effectively managing and controllingplan progress data. The invention belongs to the technical field of engineering construction, and the system is characterized in that the system at least comprises a BIM coding standard establishmentmodule used for establishing a unified BIM coding standard; a BIM model establishing module which is used for establishing a BIM model; an engineering construction plan generation module which is used for generating an engineering construction plan based on the BIM model; a plan displaying and compiling module which is used for displaying and compiling a plan based on a BIM model; a BIM model changing module; a progress feedback module: after plan editing is completed, the actual progress is obtained in real time; a plan progress simulation module; and an analysis module which is used for analyzing progress plan influence factors.

Description

Technical field: [0001] The invention belongs to the technical field of engineering construction, and in particular relates to a BIM model-based engineering construction schedule control system and method. Background technique: [0002] At present, BIM at home and abroad has entered a stage of rapid development. Although our country started late, the development trend of BIM has become clear. Enterprises began to accelerate BIM-related data mining, focusing on the application of BIM in engineering quantity calculation, bidding decision-making, etc., and practicing BIM integrated project management and control, post-maintenance, etc. [0003] The whole cycle of project construction involves the influence of project planning, design, procurement, logistics, construction, commissioning and other factors. The complexity is increasing, and the requirements for the professional level of project schedule control personnel are getting higher and higher. The traditional way of form...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/06G06Q50/08G06F3/0484G06F3/0486
CPCG06F3/0484G06F3/0486G06Q10/063114G06Q10/063116G06Q10/06312G06Q10/06313G06Q50/08
Inventor 何小龙何卫红刘涛胡亚东孙利波王威王汝贤杨超张明生孔庆森段然王倩伊丁彭妙培
Owner TIANJIN CEMENT IND DESIGN & RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products