Constructional engineering progress and cost management system, computer equipment and computer readable storage medium

A construction engineering and management system technology, applied in computing, data processing applications, instruments, etc., can solve problems such as early warning of project progress and cost, manual adjustment of progress, and no forecasting methods, so as to prevent serious overdue projects and improve accuracy. , the effect of improving efficiency

Pending Publication Date: 2020-04-21
众合广汇工程咨询有限公司
View PDF12 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The above existing technical solutions have the following defects: 1. There is no effective forecasting method to warn the progress and cost of the project in advance; 2. When the project progress lags behind the construction plan, it is necessary to manually adjust the progress, resulting in low efficiency

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Constructional engineering progress and cost management system, computer equipment and computer readable storage medium
  • Constructional engineering progress and cost management system, computer equipment and computer readable storage medium

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0051] continue to refer figure 1 , the above-mentioned management system further includes a data processing and storage module 105, configured to process the above-mentioned construction project data and store it in the database.

[0052] The implementation principle of this embodiment is: set the data processing and storage module 105, process the data in various formats (such as Word documents, Excel tables, etc.) related to the project input by the above-mentioned data input module 101, and extract the progress and cost Data, contract data, etc., and processed into the format required for storage, and then stored in the local database or cloud database, so that the data can be archived and retrieved conveniently and quickly. Further, the data processing and storage module 105 is also used to store the intermediate data output by other modules, such as the prediction module 102 and the adjustment module 104, so as to exchange data with other modules, such as for the display...

Embodiment 2

[0054] continue to refer figure 1 , the above-mentioned management system further includes an early warning module 106, configured to set thresholds for construction projects according to the above-mentioned contract data, and the thresholds include progress thresholds and construction cost thresholds.

[0055] The implementation principle of this embodiment is: read the contract data stored in the database from the above-mentioned data processing and storage module 105 through the early warning module 106, which includes the preset general project of the construction project and the progress data of each sub-project, including the start time Data, end time data, and time data of each stage, and then calculate the corresponding cost according to these preset progress data to obtain the corresponding cost data, and then set the corresponding progress threshold and cost threshold to facilitate early warning according to the progress threshold and cost threshold. Then adjust the ...

Embodiment 3

[0057] The above-mentioned early warning module 106 is also used for engineering early warning according to the prediction result and the threshold.

[0058] The implementation principle of this embodiment is: obtain the prediction result from the above-mentioned prediction module 102 through the early-warning module 106, and compare the prediction result with the threshold value of the above-mentioned early-warning module 106, that is, the overall progress and cost of each sub-project and the total project at the current stage are compared with The corresponding threshold value set by the early warning module 106 is numerically compared, and if it is greater than the set threshold value, a corresponding early warning prompt is sent to the above-mentioned display module 103, so that the project management personnel can be notified in time to prevent the project from being seriously overdue.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a constructional engineering progress and cost management system, computer equipment and a computer readable storage medium. The system comprises a data input module which isused for inputting constructional engineering data which comprises the real-time cost data, progress data and contract data of constructional engineering; the prediction module is used for establishing a real-time prediction model according to the real-time construction cost data and the progress data and predicting the progress and the construction cost of the constructional engineering in real time to obtain a real-time prediction result; the display module is used for providing an operation interface and displaying the real-time progress and cost of the constructional engineering and the real-time prediction result of the prediction module; and the adjusting module is used for adjusting the progress and the construction cost of the constructional engineering according to the real-time prediction result. The method has the effects of early warning the progress and the construction cost of the project in advance and improving the progress and construction cost management efficiency ofthe constructional engineering.

Description

technical field [0001] The invention relates to the technical field of construction project management, in particular to a construction project progress and cost management system, computer equipment and a computer-readable storage medium. Background technique [0002] At present, with the acceleration of industrialization and urbanization, the construction of construction projects has become the norm. However, in some construction projects, on the one hand, due to inadequate technology and management, the construction quality is poor, there are many safety hazards and frequent accidents. In the management of construction projects, due to the scattered and unstable locations of many construction projects, and the large number of construction sites, it increases the difficulty of management of safe construction and civilized construction, as well as the difficulty of supervision of personnel and equipment; on the other hand, in construction projects , Affected by various fac...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/04G06Q10/06G06Q50/08
CPCG06Q10/04G06Q10/0631G06Q50/08
Inventor 黄驰
Owner 众合广汇工程咨询有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional