Method or accurately controlling slab in-furnace time of stepping heating furnace
A step-by-step heating furnace, precise control technology, applied in the direction of heat treatment process control, heat treatment furnace, furnace, etc., can solve the problems of great difference in time of slab furnace, affecting quality, etc., to ensure the rhythm of steel passing and the quality of heating. , Precisely control the effect of furnace time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
specific Embodiment 1
[0019] Specific embodiment 1, three furnaces produce pipeline steel, the number of steel blocks per hour for pipeline steel is 30 pieces per hour, the length of the heating furnace is 54850 mm, and the width of the slab is 1500 mm. The time required for the slab to be in the furnace is not less than 200 Minutes, in order to ensure the time in the furnace, and can also reach the maximum production rhythm, the precise control of the time in the furnace is 210 minutes, which is 3.5 hours, and is solved as follows by the method of the present invention:
[0020] S1 Determine the thickness, steel type and width of the slab according to the production requirements, the width is 1500 mm, and according to the Taitz formula and empirical formula, consider the slab thickness, steel type and width to determine the furnace time as 3.5 hours;
[0021] The length of the S2 heating furnace is 54850 mm, and the number of steel blocks per hour is 30 blocks per hour.
[0022] The number of stee...
specific Embodiment 2
[0026] Specific embodiment 2, three furnaces produce hot charging temperature ≥ 550 ℃ hot charging slab, the steel type is the steel type that does not have the time requirement in the furnace, the slab section is a 1500 mm narrow section slab, and the slab entering furnace temperature is high, 900 -1000℃ slab oxidation begins to increase sharply. In order to reduce oxidation burning loss, it is required to control the furnace time at 165 minutes as the best, and the hour-over-steel rhythm is 32 pieces / hour.
[0027] S1 Determine the slab thickness, steel type and width according to the production requirements, the width is 1500 mm, and according to the Taitz formula and empirical formula, consider the slab thickness, steel type and width to determine the furnace time as 165 minutes, 2.75 hours;
[0028] The length of S2 heating furnace is 54850 mm, and the number of steel blocks per hour is 32 per hour.
[0029] The number of steel blocks loaded in a single furnace of S3 is 2...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com