A construction method and technology for arch bridges, which can be used in the construction of arch bridges, bridges, bridges, etc., and can solve the problems of low closing precision, difficult construction of arch bridges, and long construction period
Active Publication Date: 2019-10-25
武汉精潮钢结构有限公司
View PDF5 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
However, in the construction process of the existing arch bridge, due to the limitation of its construction terrain conditions, the construction of the arch bridge is difficult and the construction period is long. The zero stress closure of the main span arch structure of the arch bridge is difficult and the closure accuracy is not high. use
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0030] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0031] The present invention provides a technical solution: a construction method for a steel curved arch bridge, the specific steps of which are as follows: S1: foundation pile construction: trestle bridge and platform construction;
[0032] Foundation and pier construction;
[0033] Set up 5#, 6#, 7# pier cover beam support, 5#, 6#, 7# pier cover beam construction, after the concrete elastic modulus and strength reach the design value, stretch the prestresse...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
PUM
Login to View More
Abstract
The invention discloses a construction method of a steel curved arch bridge and belongs to the technical field of bridge construction. The construction method comprises the following specific steps that S1, foundation pile construction is conducted, specifically, a trestle bridge and a platform are constructed; S2, a main arch frame is constructed, specifically, arch foot section pre-embedded steel arch rib positioning steel members are mounted; S3, vault supporting mounting is constructed, specifically, closure section steel pipes are mounted, and after the line type is adjusted, steel pipesare welded; S4, pier uprights are mounted, specifically, concrete in lower pipes is symmetrically pumped; S5, a bridge deck support is mounted, specifically, bridge deck slabs are symmetrically mounted on the upstream and the downstream in the axial direction of the bridge from the two ends of a main arch and a subarch in a midspan mode; and S6, bridge deck pavement construction is conducted, specifically, bridge deck pavement auxiliary projects are symmetrically constructed, suspender cable force is copied and adjusted to a design value, steel pipe protective surface paint spraying coating isconducted, and after construction is completed, completed bridge testing and acceptance are conducted. Construction is conducted in strict accordance with the construction scheme and construction rules, control over stress and deformation during arch frame erecting can be guaranteed, and arch bridge midspan high-precision closure is guaranteed.
Description
technical field [0001] The invention discloses a construction method for a steel curved arch bridge, and specifically belongs to the technical field of bridge construction. Background technique [0002] The arch bridge is a kind of bridge that uses the arch as the main load-bearing component in the vertical plane, and the arch bridge has the characteristics of long spanning distance, high space utilization rate, material saving and beautiful appearance. The arch frame is a key part in the construction of the support. The arch frame needs to be built to support all or part of the arch ring and its upper weight when the cast-in-place concrete arch bridge is used. However, in the construction process of the existing arch bridge, due to the limitation of its construction terrain conditions, the construction of the arch bridge is difficult and the construction period is long. The zero stress closure of the main span arch structure of the arch bridge is difficult and the closure a...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.