Construction method of water-discharge temporary bridge for high-flow-rate and high-rise-degree river channel
A construction method and high-velocity technology, applied to bridges, movable bridges, bridge forms, etc., can solve problems such as potential safety hazards and high bridge deck traffic, and achieve the effects of high safety, reduced length, and reduced height
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0035] The present invention will be described in detail below in conjunction with the drawings.
[0036] The invention provides a construction method of a temporary bridge for a river with high flow velocity and large increase, including the following steps:
[0037] The first step is to construct pile foundations in the river course. There are several groups of pile foundations evenly distributed in the middle of the river course. Each group of pile foundations includes two, namely the first pile foundation and the second pile foundation. Among them, the first pile foundation Placed at the upstream of the river, the second pile foundation is placed at the downstream of the river, such as figure 1 As shown, when building:
[0038] First, build a work platform in the river:
[0039] Two flat boats are connected side by side through I-beams to form work platforms 1-7, and a gap is set between the two flat boats, and the size of the gap is determined according to the technological dimen...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com