An operating platform, offshore wind power technology, applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve the problems of high labor cost, low construction efficiency, low reliability, etc., achieve fast turnover, improve construction efficiency, and safety. high sex effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] Such as Figure 1-3 As shown, a kind of integrated working platform for offshore wind power construction of the present invention includes:
[0043] The platform main structure 40; the platform main structure is composed of truss connections; the platform main structure 40 is provided with a specified number of holes arranged symmetrically;
[0044] The pavement beam 20; the pavement beam is welded on the platform main structure; and the pavement beam reserves the position of the hole;
[0045] A pavement panel 10; the pavement panel is welded on the pavement beam 20;
[0046] The shoulder pole beam 60 ; the shoulder pole beam is arranged above the hole, and the two ends of the shoulder pole beam and the platform main structure 40 are connected by bolts through connecting flanges respectively provided thereon. Such as figure 2 As shown, each pole beam 60 wherein is arranged symmetrically. The shoulder pole beam is used to bear the weight of the entire operation pla...
Embodiment 2
[0054] Based on the above-mentioned work platform, the present application also provides a construction method for an integral work platform for offshore wind power construction, and the method includes steps:
[0055] A. Production of the work platform on land:
[0056] A1. The space truss structure formed by connecting the trusses on land is used to manufacture the platform main structure, wherein a specified number of holes symmetrically arranged are reserved in the platform main structure during production;
[0057] A2. Weld the pavement beam on the upper part of the completed platform main structure; and reserve the position of the hole on the pavement beam; weld the pavement panel on the upper part of the pavement beam, and The guardrail is welded around the structure; and the reserved hole runs through the platform main structure, the pavement beam and the pavement panel;
[0058] A3. Install the shoulder pole beam above the reserved hole; the two ends of the shoulder po...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com