Construction method of continuous three layer pavement of bottom base layer, lower base layer and upper base layer of cement stabilized macadam

A technology of cement-stabilized gravel and construction method, which is applied in the construction of three-layer continuous paving of the lower base and upper base, and in the field of cement-stabilized gravel subbase, which can solve problems such as roadbed damage, large manpower and material resources, and complicated maintenance.

Active Publication Date: 2015-05-20
CHINA FIRST HIGHWAY ENG +1
View PDF4 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, during the construction process in the rainy season, it is very easy to have quality hazards, which not only cause serious defects in the appearance of the road surface, but also cause damage to the roadbed when the rain is strong, and spend a lot of maintenance costs during the road operation period. huge economic losses
For construction during the rainy season, most construction companies still have no good countermeasures except passively avoiding construction in rainy days and doing a good job of drainage
On the other hand, the traditional construction technology usually adopts the method of cement stabilizing the subbase, spreading and curing the base, and then paving and maintaining the construction. Not only the construction efficiency is low, the construction period is long, and the maintenance is more complicated. Invest a lot of manpower and material resources in maintenance

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0046] A certain pavement project, the starting and ending pile number of the route is K232+126.364-K243+480, the construction mileage length is 11.3km, two-way six lanes, integral subgrade, subgrade width 32 meters, design speed: 80km / h, design axle load BZZ-100, The design of pavement structure layer is: 5cmSMA-16+7cmAC-20+8cmATB-25+30cm water stable base + 15cm water stable subbase (20cm water stable subbase). After the project department entered the site, the construction period was reversed according to the contract node construction period requirements. The construction period for the water-stabilized subbase and the base course with a total of 300,000 tons of mixed materials was 3 months. At the same time, the construction area had a lot of rainfall, and July and August were rainy seasons. In addition, due to the influence of the subgrade unit's handover and inspection, the construction work area is limited. If the conventional construction method is adopted, the cement...

Embodiment 2

[0048] For a section of expressway, according to the actual situation on site: tight construction period, heavy tasks, long rainy season, etc., the water-stabilized subbase and base were constructed with three layers of continuous paving, and the construction effect was good. At the same time, the water-stabilized subbase and upper and lower The amount of cement slurry bonding between the base layers, the amount of cement is 1.5kg / m 2 , a total cost saving of about 500,000 yuan, and a health care cost saving of about 600,000 yuan, the economic benefits are considerable.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of the continuous three layer pavement of a bottom base layer, a lower base layer and an upper base layer of cement stabilized macadam. The method comprises the steps of construction lofting; mixed material mixing and transportation; pavement and rolling; and joint connection treatment, wherein in the pavement and rolling step, two pavement machines take place in parallel, a lower supporting layer is wetted by sprinkling water and waterlogging is avoided, and the pavement of the bottom base layer of the cement stabilized macadam is carried out; when the first pavement machine carrying out the pavement by a distance of 5-10 meters, the second pavement machine begins carrying out the pavement, and always keeps the distance of 5-10 meters with the first pavement machine in a pavement process, and the rolling is instantly carried out after pavement and finishing; when a construction section of 200 meters is finished after the pavement and the rolling of the bottom base layer, the pavement of the lower base layer is carried out, and the rolling is instantly carried out after the pavement and finishing; after a construction section of 190 meters is finished after the pavement of the lower base layer, the pavement of the upper base layer is carried out, the lower base layer is constructed under the control of the pavement and rolling, and a construction section of 180 meters is carried out after the pavement of the upper base layer. According to the construction method, the working period is greatly shortened, and the caking property of the integrated structure is high; meanwhile, the maintenance cost of the two layers is saved, and the maintenance is relatively simple.

Description

technical field [0001] The invention belongs to the technical field of civil engineering, and relates to a construction method of a cement-stabilized macadam base for expressways, and more particularly relates to a construction method for three-layer continuous laying of a cement-stabilized macadam base, a lower base and an upper base. Background technique [0002] With the acceleration of highway construction in our country, in order to improve economic benefits, more and more construction projects are carried out in the rainy season. However, during the construction process in the rainy season, it is very easy to have quality hazards, which not only cause serious defects in the appearance of the road surface, but also cause damage to the roadbed when the rain is strong, and spend a lot of maintenance costs during the road operation period. Enterprises bring huge economic losses. For construction during the rainy season, most construction companies still have no good count...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01C7/10
CPCE01C7/14E01C7/142
Inventor 王振江任伟涛蔡新宁马永青潘祯王顶峰景作为王腾飞黄立国
Owner CHINA FIRST HIGHWAY ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products