Double-platform scaffold-free elevator installation method
A technology without scaffolding and installation methods, which is applied to elevators, transportation and packaging, elevators, etc. in buildings, can solve the problems of difficulty in shortening the construction period, consume more electric energy, and long construction period, so as to reduce the construction period and save The effect of reducing the cost of building and dismantling and reducing the running time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] like Figure 1-3 As shown in the figure, a method for installing a double platform elevator without scaffolding is characterized in that the installation procedure is: making a template and setting out the line--machine room equipment installation--temporary platform erection--pit equipment installation--car platform assembly-- Down-moving platform installation - traction type and speed limiter installation - slow train debugging - using platform construction - platform removal and installation of counterweight - car hardcover - express train debugging, as follows:
[0036] Make the model and pay off: Make the model frame according to the actual dimensions of the elevator car, counterweight, guide rail and other components, install the model frame in the machine room, and then hang the plumb line according to the model frame, and stabilize the plumb line;
[0037] Equipment installation in the machine room: install traction machines, speed limiters, and control cabinets...
Embodiment 2
[0049] A project includes the installation of 4 high-speed elevators, the length of the elevator shaft is 70m, and the maximum running speed of the elevator is 6m / s. The contract elevator construction period for elevator installation is 60 days. Since the civil construction progress is 18 days later than planned, the actual construction period for the elevator installation is only 42 days. The traditional scaffolding elevator installation method cannot complete the elevator installation task within the specified construction period. The technicians conducted many researches and discussions on the plan, and formulated a double platform elevator installation method:
[0050] The elevator installation procedures adopted are: making templates and laying out lines - machine room equipment installation - temporary platform erection - pit equipment installation - car platform assembly - lower platform installation - traction type and speed governor installation ——Slow car debugging——Ut...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com