Method for positioning temporary middle walls in large-section tunnel supporting structure of formation with soft top and hard bottom
A positioning method and technology of support structure, applied in tunnels, tunnel linings, underground chambers, etc., can solve problems such as large deformation, unsafe accidents, excessive temporary support, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0053]The structure and method of the present invention will be further described below with reference to the accompanying drawings.
[0054] Such as figure 1 As shown, the position of the temporary middle wall in the excavation and support structure of the long-span tunnel used for the upper soft and lower hard stratum surrounding rock, the support structure includes advance support, initial Whether to set up a partition wall shall be analyzed based on the hard stratum boundary conditions.
[0055] The actual use process is as follows:
[0056] Step 1: Apply the force method in structural mechanics and the force characteristics of primary support to analyze the force state of the upper soft and lower hard stratum structure, including the following aspects:
[0057] (1) Analysis of the stress state of the initial support of the tunnel when there is no middle wall
[0058] Since the lining structure is subjected to relatively large vertical and horizontal pressures, under th...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com